ML19309H816
| ML19309H816 | |
| Person / Time | |
|---|---|
| Site: | Marble Hill |
| Issue date: | 05/06/1980 |
| From: | Wildon J Office of Nuclear Reactor Regulation |
| To: | Office of Nuclear Reactor Regulation |
| References | |
| NUDOCS 8005190752 | |
| Download: ML19309H816 (3) | |
Text
--
8 0 051C076'2.
MEETING
SUMMARY
DISTRIBUTION Docket File J. Knight wNRC PDR S. Hanauer Local PDR R. Tedesco TIC R. Bosnak NRR Reading S. Pawlicki LWR #3 File F. Schauer H. Denton K. Kniel E. Case T. Novak H. Berkow Z. Rosztoczy D. Ross W. Butler D. Vassallo V. Benaroya D. Skovholt R. Satterfield J. Stolz V. Moore R. Baer W. Kreger
- 0. Parr M. Ernst L. Rubenstein F. Rosa S. Varga R. Denise C. Heltemes EP Branch Chief W. Haass G. Chipman R. Houston J. Collins L. Crocker T. Murphy ACRS (16)
G. Lear F. Williams B. Youngblood R. Mattson R. Jackson R. DeYoung L. Hulman Project Manager J. N. Wilson Attorney, ELD NRC Particitants: J. N. Wilson M. Rushbrook J. J. Harrison IE (3)
J. Gilray BCC: Applicant & Service List l
l l
l j
pA #f 00
,,(
9(o, UNITED STATES g
g NUCLEAR REGULATORY COMMISSION g
-E WASHINGTON, D. C. 20655 0
r.;
/
MAY 6 1980 Docket Nos. : STN 50-546 and STN 50-547 APPLICANT: Public Service Company of Indiana FACILITY:
Marble Hill Nuclear Generating Station
SUBJECT:
SUMMARY
OF MEETING HELD ON APRIL 11, 1980 A meeting was held in Bethesda, Maryland with representatives of Public Service Indiana and Sargent and Lundy.
The purpose of the meeting was to discuss the revised Quality Assurance Program description for Marble Hill.
A list of attendees is provided in Enclosure 1.
In a letter from L. S. Rubenstein to S. W. Shields dated April 1,1980, we required PSI to prepare a consolidated quality assurance program description for Marble Hill and incorporate the enclosed request for idditional informa-tion. During the meeting, we reviewed a draft of PSI's proposed consolidated report. We also discussed PSI's response to each of the 22 questions issued on April 1, 1980. As a result of this review we developed additional questions on the revised quality assurance program description. This second set of questions was issued to PSI on April 28, 1980.
f. Q, 41 r
N. Wilson, Project Manager i ensing Branch No. 1 Division of Licensing
Enclosure:
Attendance List
MARBLE Hill 4-11-80 ATTENDANCE LIST NRC - Staff Jerry N. Wilson J. J. Harrison J. Gilray Public Service Indiana C. E. Chmielewski S. Brewer J. Norris Sargent & Lundy Engineers A. M. Weiss
- 0. Zaben ENCLOSURE
..-.