r POWER AUTHORITY OF THE STATE OF NEW YORK JAMES A. FITzPATRicx NUCLEAR POWER PLANT S
JOHN D. LEONARD, JR.
P.O. BOX 41 Resident Manager Lycoming, Nm York 13093 31s-342 3840 February 14, 1980 SERIAL: JAFP-80-138 Mr. Boyce H. Grier Di recto r United States Nuclear Regulatory Commission Region 1 631 Park Avenue King of Prussia, PA 19406
SUBJECT:
NRC ISE Bulletin 79-18 Audibility Problems in High Noise Areas
REFERENCE:
Letter to NRC Dated October 17,1979, (JAFP-79-566) from John D. Leonard, Jr.
Dear Mr. Grier:
i in the referenced response, it was stated that the corrective actions for accessible areas would be completed by February 15, 1980 (120 days from the date of the response).
However, some of the material ordered from Gaitronics Corporation has not yet been received.
The shipment is due this week.
As soon as the equipment is received, the plant staff will complete the corrective ar.tions.
Therefore, an extension of the completion date to March 7,1980 is requested.
As previously stated in the referenced letter, the areas which are considered inaccessible due to high radiation during plant operation, will be completed during the next refueling outage.
Very truly yours,
)