ML19309E204

From kanterella
Jump to navigation Jump to search
Joint Motion Re Particularization of Contentions,Per ASLB 800305 Order.Moves for Clarification of 30-day Limitation & for Extension Until 800404 If Limitation Applies
ML19309E204
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 04/02/1980
From: Hoefling R, Latham S
NRC OFFICE OF THE EXECUTIVE LEGAL DIRECTOR (OELD), SHOREHAM OPPONENTS COALITION
To:
Atomic Safety and Licensing Board Panel
Shared Package
ML19309E203 List:
References
NUDOCS 8004210009
Download: ML19309E204 (2)


Text

__

O UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of

)

)

LONG ISLAND LIGHTING COMPANY

)

Docket No. 50-322

)

(Shoreham Nuclear Power Station, )

Unit 1)

)

JOINT MOTION OF SHOREHAM OPPONENTS COALITION (SOC) AND NRC STAFF WITH REGARD TO PARTICULARIZATION OF SOC CONTENTIONS In its " Order Ruling on Petition of Shoreham Opponents Coalition" dated March 5, 1980, (Order) the Atomic Safety and Licensing Board granted the Shoreham opponents Coalition (SOC) leave to further particularize certain of its contentions.

The Board further directed that:

Petitioner shall file its response to this Order as soon as possible and in no case no later than 30 days from this Order.

(Order, page 25. )

It is SOC's position that the Board's 30 day time limitation applies to defects in standing but not to the Board's request for further particularization.

SOC will elaborate on its position regarding particularization in its filing which will accompany the submission of affidavits on the standing question.

In view of SOC's perceived ambiguity in this language, SOC moves the Board to clarify the Order in this regard.

8 0 04 2100 on,

D 0

Should the Board rule that the 30 day limitation does apply to contention particularization, SOC and the NRC Staff would jointly move the Board to extend that time.

At a meeting held between representatives of SOC and the NRC Staff on March 20, 1980, discussions were commenced regarding the partizularization of the SOC contentions.

Efforts at particularization will extend beyond the 30 day period set down by the Board in its Order.

To this end, a meeting has been scheduled for the week of April 14, 1980 between NRC Staff and SOC.

If the 30 day period set down by the Board does apply to contention particularization and in light of the activities discussed above and in the hope that a stipulation with regard to particularization of contentions can be reached, SOC and the NRC Staff jointly move the Board to extend for a period of 60 days from April 4, 1980, the time within which SOC must particularize certain of its contentions.*

Should the Board be disposed to granting such an extension, the Staff would undertake to inform the Board from time to time as to the status of these efforts.

Respectfully submitted, NRC AFF SHOREHAM OPPONENTS COALITION n.fA M(]h Y

/d t

956hard K.

Hoefling StephenpB. Latham Di April

$2s 1980

  • The Applicant has indicated that it has no objections to this time extension.