Provides Status of Response to NRC 800327 Request for Commitment to Installation of Auxiliary Feedwater Sys & safety-grade Sys for Automatic Initiation.Development of safety-grade Sys Underway
ML19309E132
Person / Time
Site: Maine Yankee
Issue date: 04/14/1980
From: Groce R
Maine Yankee
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
WMY-80-65, NUDOCS 8004180438
Download: ML19309E132 (1)


Text

(

?

5:

l,_.9 I

TURNPIKE ROAD (RT. 9)

$ C'*d ENGINEERING OF FICE WESTBORo, MASSACHUSETTS 01581 617-366-9011 z~# O April 14, 1980 B.3.2.1 United States Nuclear Regulatory Commission Washington, D.C.

20555 Attention: Office of Nuclear Reactor Regulation Mr. Darrell G. Eisenhut, Director Division of Operating Reactors

Reference:

(a) License No. DPR-36 (Docket No. 50-309)

(b) USmC Letter to MYAPC dated March 27, 1980 (c) USWC Letter to MYAPC dated December 21, 1979 (d) MYAPC Letter to USNRC dated February 1, 1980 (WMY 80-19)

Subject:

Automatic Initiation of Auxiliary Feedwater System (AFWS)

Dear Sir:

This letter is written in response to your letter, Reference (b), in which you request that Maine Yankee commit to: (1) install a control grade system for automatic initiation of AFWS flow by June 1,1980; and (2) install a safety-grade system prior to January 1,1981.

Maine Yankee has installed the required control grade hardware to allow for automatic initiation of AFWS flow, and has awaited E C approval to implement the system pursuant to your letter, Reference (c). Maine Yankee comits to complete the implementation to enable operation not later than June 1, 1980. This installation was detailed in our letter, Reference (d).,

Maine Yankee is presently developing a safety-grade system for automatic initiation of AFF flow, which will be submitted for your review in a timely manner. Implementation of the safety-grade system by January 1,1981, will require prompt W C review, and more significantly, E C approval of our proposed design. We wish to point out that any review delay or design changes required by your staff could prevent Maine Yankee from completing the safety-grade installation by the required date.

We trust this information is satisfactory; however, if you have any questions, please do not hesitate to contact us.

Very truly yours, MAIE YANKEE ATOMIC POWER COMPANY b

Robert H. Groce Senior Engineer - Licensing RHG/kaf 800.4180438

.