Responds to IE Bulletin 79-14.Submits Mod to Paragraph 4 of to Nrc,Per 800306 Telcon.All Seismic Support Nonconformance Will Be Restricted Prior to Restart
ML19309D512
Person / Time
Site: Maine Yankee
Issue date: 03/07/1980
From: Moody D
Maine Yankee
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
IEB-79-14, NUDOCS 8004100406
Download: ML19309D512 (1)


Text

. p,2:'====%

g MAIRE HARHEE T~3 E5:DW

  • TURNPIKE ROAD (RT. 9)

N.,

S 1 1"' i~

ENGINEERING OFFICE WEST 80RO, M ASSACHUSETTS 01581 8"-*-'"

    1. g March 7,1980 B.4.1.1 United States Nuclear Regulatory Commission Office of Inspection & Enforcement Region I 631 Park Avenue King of Prussia, Pennsylvania 19406 Attention:

Mr. Boyce H. Grier, Director

References:

(a) License No. DPR-36 (Docket No. 50-309)

(b) USNRC Letter to MYAPC dated July 2,1979 I&E Bulletin No. 79-14; Revision 1 dated July 18, 1979; and supplement dated August 15, 1979 (c) MYAPC Letter to USNRC dated July 24, 1979 (d) MYAPC Letter to USNRC dated September 25, 1979 (e) MYAPC Letter to USNRC dated May 2,1979 (f) MYAPC Letter to USNRC dated November 7,1979 (g) USNRC I&E Letter to MYAPC dated November 19, 1979 (h) HYAPC Letter to USNRC dated November 30, 1979 (i) MYAPC Letter to USNRC dated March 4,1980

Dear Mr. Grier:

Subject:

Maine Yankee I&E Bulletin 79 Status and Scheduled Completion

~ As a result of several telephone conversations on March 6,1980 between Tim Martin of your office and me with our consultants from Earthquake Engineering Services and your consultants from the NRC Headquarters Staff, I am forwarding the following modification to paragraph 4 of Reference (i):

4.

All nonconformance to seismic supports identified in this effort which we determine to affect system operability will be rectified privr to restart from the current outage.

All shims required to meet original design criteria which will be inaccessible af ter startup will be installed prior to restart.

This will leave 30 to 40% of the shimming operation to be completed during March 1980 in accessible areas af ter restart.

These will include shims for gaps equal to or less than 3/8".

We have determined that shims to be added af ter plant restart do not af fect system operability.

If you require additional information on this subject, please contact us at your convenience.

Very truly yours,