Commits to Install Backup Sys to Normal Instrument Air Supply for Pressurizer Power Operated Relief Valves,In Response to Lessons Learned Review Team.Installation Will Be Completed by End of Oct 1980 Second Refueling Outage
ML19309C283
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 03/26/1980
From: Clayton F
ALABAMA POWER CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
NUDOCS 8004080403
Download: ML19309C283 (1)


Text

AMcama Pow 2r Corrpany 600 North 10tn Stre;t Post Offica Box 2641 Birmingham. Alabama 35291 Te:ephone 205 323-5341 k

h hbo?t^c"le';@n, Alabama Power m roamm e.coc ssem March 26, 1980 Docket No. 50-348 Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission

'4 ashing ton, D.C.

20535 Attn:

Mr. Darrell G. Eisenhut

Dear Mr. Eisenhut:

As a result of discussions held with the NRC Lessons Learned Review Team on February 29, 1980, and telephone conversations on March 21, 1980, Alabama Power Company commits to installing a backup system to the normal instrument air supply for the pressuriser power operated relief valves (PORV).

The design will assure that air is available at all times to operate the PORV's.

Installation of the backup system will be completed by the end of the Unit 1 second refueling outage scheduled to begin in October, 1980.

If you have any questions, please contact us.

Yours very truly, Yjgt cf F.T.klayton Jr.

FLCJr/BDM:bhj cc:

Mr. R. A. Thomas Mr. C. F. Trowbridge l