ML19309B917

From kanterella
Jump to navigation Jump to search
Advises That,Due to Studies of Electric Svc Requirements & Const Expenditure Forecasts,Fuel Load Date Was Deferred from 831231 to 851231.Commercial Operation Date Scheduled for 860531.FSAR & Environ Rept Submittal Scheduled for 821231
ML19309B917
Person / Time
Site: Beaver Valley
Issue date: 03/26/1980
From: Woolever E
DUQUESNE LIGHT CO.
To: Stolz J
Office of Nuclear Reactor Regulation
References
NUDOCS 8004070336
Download: ML19309B917 (1)


Text

'Af (412) 456-6000 435 54mm Avenue ZT'e#*

March 26, 1980 Director of Nuclear Reactor Regulation United States Nuclear Regulatory Cmmission Division of Project Management Washington, D.C. 20555 ATTENTION:

Mr. John F. Stolz, Chief Light Water Reactors, Branch No. 1

SUBJECT:

Beaver Valley Power Station - Unit No. 2 Docket No. 50-412 CPPR-105 Gentlemen:

Due to studies of electric service requirements and construc-tion expenditure forecasts over the next several years we have deferred the scheduled fuel load date of Beaver Valley Power Station Unit No. 2 from December 31, 1983 to December 31, 1985.

The cmmercial operation date is scheduled for May 31, 1986. Our schedule for submission of the Final Safety Analysis Report and Environmental Report is December 31, 1982.

DUQUESNE LIGHT COMPANY By I

E. J. Woolever Vice President l

cc: John Angelo l