Responds to NRC Re Violations Noted in IE Insp Rept 50-334/79-18.Requests Extension Until 800401 for Compliance Re Item 79-18-05
ML19309B802
Person / Time
Site: Beaver Valley
Issue date: 01/29/1980
From: Dunn C
DUQUESNE LIGHT CO.
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML19309B799 List:
References
NUDOCS 8004070199
Download: ML19309B802 (1)


Text

___-__ ___ -

as....

'Af M

Hm 4564000 435 Sistn Avenue 52 January 29, 1980 United States Nuclear Regulatory Commission Office of Inspection and Enforcement Atta: Boyce H. Grier, Regional Director Region I 631 Park Avenue King of Prussia, Pennsylvania 19406

Reference:

Beaver Valley Power Station, Unit No. 1 Docket No. 50-334, License No. DPR-66 I.E. Inspection No. 79-18 Enforcement Item 79-18-05

Dear Mr. Grier:

In our response to the above referenced inspection dated December 19, 1979, we stated that the date for which full compliance would be achieved for

- Item 79-18-05 would be January 31, 1980.

This letter is to request an extension of the full compliance date until April 1, 1980.

We have determined that the scope of work to update the station files to incorporate revisions required due to design changes, is mu;h greater than our original review indicated.

This work is progressing on a timely basis with approminately 25% of the work completed.

If you have any questions, please contact my office.

  • /ery truly yours, C. H. Dunn Vice President, Operations 8004.070l99

- -