Summary of Regulatory Review Committee 760915 Meeting 54 Re Proposed Revision 1 to Reg Guide 1.68 Initial Test Programs for Water Cooled Reactor Power Plants & Proposed Reg Guides 1.68.X & 1.105
ML19308C851
Person / Time
Site: Crane Constellation icon.png
Issue date: 09/21/1976
From: Case E
Office of Nuclear Reactor Regulation
To: Gossick L
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
References
RTR-REGGD-01.068, RTR-REGGD-01.105, RTR-REGGD-1.068, TASK-OS, TASK-RS-507-4, TASK-TF, TASK-TMR NUDOCS 8002070601
Download: ML19308C851 (2)


Text

_ - _ _ - _ _

UNITED STATES f

\\

NUCLEAR REGULATORY COMMIS$10N g

j wAsMINGTON, D. C. 20005

('

September 21, 1976 Lee V. Gossick Executive Director for Operations REGULATORY REQUIREMENTS REVIEW COMMITTEE MEETING NO. 54, SEPTEMBER 15, 1976 The Comittee reviewed:

1.

Proposed Revision 1 to Regulatory Guide 1.68, " INITIAL TEST PROGRAMS FOR WATER-COOLED REACTOR POWER PLANTS." and recomended approval.

The Comittee characterized this guide as Category 1 - No backfit.

2.

Proposed Regulatory Guide 1.68.X, (RS-507-4) " INITIAL STARTUP TEST PROGRAM TO DEMONSTRATE RENOTE_ SHUTDOWN. CAPABILITY FOR WATER-COOLED NUCLEAR POWER PLANTS," and recomended approval ~~ ^~

subject to the following coment:

a.

The terminology and definitions utilized in this guide should be consistent with those utilized in Standard Technical Specifications.

For operating license applications now under review, the Comittee characterized this guide as Category 3 - backfit required.

For operating reactors, the Comittee characterized this guide as Category 2 - Futther staff consideration of individual cases required Tn order to determine the need for backfitting.

3.

Proposed Revision to Regulatory Guide 1.105 [RS(DS 506-41)],

" INSTRUMENT SETPOINTS," and recomended approval subject to the following coment:

a.

Appropriate language should be included in the guide concerning the required accuracy of instrumentation set points, taking into account the language and limitations included in Standard, Technical Specifications.

The Comittee characterized this guide aLCategory 2 - Furthet staff consideration of individual cases requiredTn~ order to determine the need for backfitting.

l 8002070dO[

g

2-4.

Proposed Revision to " TORNADO MISSILE CRITERIA," Standard Review Plan 3.5.1.4, and recomended approval with the suggestion that the staff vigorously pursue additional work in this area along the lines of the Comittee coments, especially those concerning the selection of a design basis tornado having a higher probability of occurrence.

j

.f Edson G. Case, Chaiman Regulatory Requirements Review Comittee cc:

B. Rusche cc:

H. Shapar S. Hanauer F. Schroeder H. Kouts S. Varga E. Volgenau T. Rehm T. Murley M. Grossman R. Minogue R. Cunningham J. Davis L. Rouse R. Boyd DRL ACs R. Heineman SS ads V. Stello OR ads

(

H. Denton SS & EA ads B. Grier l

-. -