Text
a UNITED ' STATES NUwEAR REGULATORY COMMisslON W ASHINGTON, D. C. 20555 ocT 3 1975 Lee V. Gossick Executive Director for Operations REGULATORY REQUIREMENTS REVIEW COMMITTEE MEETING NO. 37, SEPTEMBER 26, 1975 The Comittee reviewed the following items:
1.
Proposed regulatory Guide 1.100, PREOPERATIONAL AND INITIAL STARTUP TESTING OF FEEDWATER AND CONDENSATE SYSTEMS FOR
-BOILING WATER REACTORS, and recomended approval subject to the following comments:
This guide should be issued as a subset to Regulatory),
a.
Guide 1.68 (similar to iihe subsets of tEl 70 series
~
rather than a separate guide.
- b. ~ Paragraph C1f (page 4 of draft) should be clarified as to acceptable simulations of malfunctions in the control system and plant transients.
The Comittee characterized this guide as Category 1 - No backfit.
+
2.
Proposed Regulatory Guide 1.97, INSTRUMENTATION FOR LIGHT-WATER-COOLED NUCLEAR POWER PLANTS TO ASSESS PLANT CONDITIONS DURING AND FOLLOWING AN ACCIDENT and recommended approval. The Comittee characterized this gu.ide as Category 1 - No backfit.
Items 3 and 4 of the agenda were deferred to the+next meeting.
Edsond. Case Chairman, Regulatory Requirements l
Review Committee cc:
B. Rusche G. Arlotto H. Kouts F. Schroeder D. Knuth R. Heineman S. Hanauer S. Varga H. Shapar T. Rehm J. Gallo R. Cunningham R. Boyd L. Rouse R. Minogue; RL ads J.' Davis TR ads D. Eisenhut 800207053 3 y
.