QA Program Insp Rept 99900399/79-01 on 791126-28.No Noncompliance Noted.Major Areas Inspected:Implementation of 10CFR50 App B Criteria & Applicable Codes & Stds,Including QA Manual Review
ML19308C774
Person / Time
Issue date: 12/14/1979
From: Foster W, Hunnicutt D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19308C772 List:
References
REF-QA-99900399 99900399-79-1, NUDOCS 8002010322
Download: ML19308C774 (3)


Text

>

e O

U.S. NUCLEAR REGULATORY COMr!ISSION OFFICE OF INSPECTION AND ENFORCEMENT REGION IV Report No.

99900399/79-01 Program No. 51400 Company:

American Insulated Wire Corporation 36 Freeman Street Pawtucket, Rhode Island 02862 Inspection at:

Pawtucket, Rhode Island, and Attleboro, Massachusetts Inspection Conducted: November 26-28, 1979

/

/2/8/77 Inspector

___W.E. Foster, Contractor Inspector

/ Date Wut 4

ComponentsSection II

')

Vendor Inspection Branch Approved by:

f)7

< m a'y[

/2//f/77 D. M. Hunnicutt, Chief

' Date ComponentsSection II Vendor Inspection Branch Summary:

Supported a reactive effort by Region I personnel on November 26-28, 1979 (99900399/79-01).

Areas Inspected:

Implementation of 10 CFR 50, Appendix B, criteria and applicable codes and standards including a quality assurance manual review.

The inspection involved seventeen (17) hours on site.

Results:

In the area inspected, no deviations or unresolved items were identified.

840201W 11 mm.nto

o 6

2 DETAILS SECTION A.

Persons Contacted F. Amaral, Manaaer-Production G. DuBois, Sales Manager-Electrical Distribution

  • W. Firth, Manager-Quality Assurance
  • A. T. Galkin, Secretary
  • ll. Galkin, General Manager
  • 11. S. Galkin, Vice President-Marketing and Sales
  • I.

S. Galkin, President

  • S.

Shapiro, Technical Director

  • Attended the combined initial management meeting and exit interview.

B.

Initial Management Meeting and Exit Interview 1.

Objectives l

An initial management meeting and exit interview was conducted to acquaint the vendor's management with the NRC responsibility to i

protect the health and safety of the public and to inform them of certain responsibilities imposed on vendors by the " Energy Reorgan-ization Act of 1974" (Public Law 93-438). Those in attendance are denoted in paragraph A.

2.

Method of Accomplishment The preceding objectives were accomplished by:

a.

Describing the historical events that indicated the need for the Vendor Inspection Program.

b.

Explaining the inspection base and how the inspections are conducted.

c.

Describing how inspection results are documented and how proprietary items are handled, including the vendor's opportunity l

to review the report for the purpose of identifying items con-sidered to be proprietary.

i d.

Describing the vendor's responsibility in responding to identi-

.fied enforcement items relating to:

(1) Correction of the identified deviation.

(2) Action to be implemented to prevent recurrence.

I l

I l


..-----r.

~.----.---.---:-

-- =.

J i

I 1

3 (3) The dates when (1) and (2) above will be implemented or i

completed.

Explaining that all reports and communications are placed in c.

the Public Document Room.

1 f.

Explaining the publication and function of the Licensee Con-tractor and Vendor Inspection Status Report, NUREG-0040.

g.

Explaining that my activities during this inspection were in a support role to NRC personnel from Region I and subsequent routine inspections would be performed by NRC personnel from Region IV.

3.

Findings n

The President of American Insulated Wire Corporation recognizes the importance of quality assurance and stressed that its necessity was a direction from his office. He also emphasized pride in the reputa-tion of the company and stated he would not permit its reputation to be compromised.

C.

QA Manual Review 1.

Objectives 4

The objectives of this area of the inspection were to verify that the QA Manual addressed the eighteen (18) criteria of Appendix B to 10 CFR 50 and had been endorsed by management as an authoritative document.

2.

Method of Accomplishment The preceding objectives were accomplished by reviewing the Quality Assurance Manual dated June 25, 1979.

3.

Findings Within this area of the inspection, no deviations or unresolved items were identified.

During the course of the inspection, it was observed that:

(1) Manufacturing also takes place at Attleboro, Massachusetts, (2) Several nuclear orders are currently in work, and (3) Purchase orders are placed by the agent / utility with a distributor, who in turn, initiates a purchase order which goes to American Insulated Wire Corporation.

i m-