Final Deficiency Rept Re Limited Heat Number on A-36 Steel. Cause Unstated.Removal of Supports Initiated.Deviation Disposition Request Generated
ML19305E367
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 03/28/1980
From: Fahrner W
DETROIT EDISON CO.
To:
References
NUDOCS 8004230489
Download: ML19305E367 (1)


Text

.

lb i

Detroit Edison 9E55=>-

March 28, 1980 EF2-48,574 Mr. James C. Keppler Regional Director Regi.on III g 3Ql U.S. Nuclear Regulatory Comission 799 Roosevelt Road Glen Ellyn, Illinois 60137

Subject:

10CFR50.55(e) Deficiency Report on A-36 Raceway Hanger Support Plate Steel.

Dear Mr. Keppler:

This letter is submitted as Detroit Edison's final report on the subject A-36 Steel purchased through L.K. Comstock for use at the Fermi II Site.

Investigations have revealed that the nonconforming material is limited to one heat number, 8018 22820, furnished by Bethlehem Steel. All supports which vere fabricated from that heat have been located and will be removed. Replacement supports will be of ASTM A516, Grade 70 plate material.

Removal work was initiated March 21, 1980, and will continue as appropriate with the construction schedule. Deviation Disposition Requests (DDR), have been generated and is the measure being employed to provide control of the noncon-forming supports until they are removed.

Further details of this investigation are contained in Detroit Edison Letter F2S80-380 with attached report, which is available at the Fermi II Site for review.

Sincerely yours, N]

W.J. Fahrner Project Manager Enrico Fermi Unit II WJF/GK/ pin cc: Mr. Victor Stello, Jr., Director Office of Inspection and Enforcement Division of Reactor Inspection Programs U.S. Nuclear Regulatory Commission Washington D.C.