Order Re or Energy Facility Siting Council 800314 Order Suspending Proceeding Until 810701.Directs Parties to Inform ASLB Re Effects of Suspension on Site Suitability
ML19305D452
Person / Time
Site: 05000514, 05000515
Issue date: 04/03/1980
From: Bowers E
Atomic Safety and Licensing Board Panel
To:
OREGON, STATE OF
References
NUDOCS 8004150092
Download: ML19305D452 (1)


Text

.

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION ATOMIC SAFETY AND LICENSING BOARD Elizabeth S. Bowers, Chairman Dr. Walter H. Jordan Dr. William E. Martin In the Matter of

)

)

PORTLAND GENERAL ELECTRIC COMPANY, )

Docket Nos. 50-514 ET AL.

)

50-515

)

(Pebble Springs Nuclear Plant,

)

Units 1 and 2)

)

ORDER RELATIVE TO STATUS OF OREGON ENERGY FACILITY SITING COUNCIL PROCEEDING By Order of March 14, 1980, the Oregon Energy Facility Siting Council stated that it was suspending it's proceeding on Pebble Springs until July 1, 1981.

It also stated that it would then reevaluate the possible continuance of it's proceeding at that time and every six months thereafter.

The Applicant acquiesced to the delay.

The parties in this proceeding are requested to inform this Board if this action affects their position relative to the con-tinuance of the NRC proceeding on site suitability.

IT IS SO ORDERED.

FOR THE ATOMIC SAFETY AND LICENSING BOARD f4Jaun

~

Elizabeth S.

bowers, Chairman Dated at Bethesda, Maryland this 3rd day of April 1980.