Interim Rept 14,Initial Approach to Power Tests (B-Series) for 791123-800222. Future Interim Repts Will Submit Results of Power Levels Above 70%
ML19305C091
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 02/22/1980
From:
PUBLIC SERVICE CO. OF COLORADO
To:
Shared Package
ML19305C090 List:
References
NUDOCS 8003250581
Download: ML19305C091 (2)


Text

~\

THE FORT ST. VRAIN INITIAL APPROACH TO POWER TESTS (B-SERIES)

INIERIM REPORT 14 Report for Period Ending February 22, 1980

  • \ .

Interim Report 8 covering the 90 day period ending August 22, 1978, re-ported the completion of all tests up to 70% of plant load. Since the Nuclear Regulatory Commission did not release the plant for operation at power levels in excess of 70%, no further Initial Approach to Pcwer Tests were performed during the 90 days ending February 22, 1980.

The Fort St. Vrain Nuclear Generating Station was accepted for commercial operation at 70% power by Public Service Company of Colorado on July 1,1979.

Future interim reports will report the results of any startup tests at power levels above 70%.