/L&

xasas ans no sucrmc commry G LEN N L. MOESTER vect entsectnr.opsmations January 25, 1980 Mr. W.C. Seidle Reactor Construction and Engineering Support Branch U.S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76012 Re:

(a) Docket No. STN 50-482 (b) GKoester letter to WSeidle dated 12/3/79 same subject Subj: Loose Spherical Bushings in Corner Lada Sway Struts

Dear Mr. Seidle:

As indicated in Reference (b), investigation and tests have been completed to determine the effect of loose spherical bushings in sway struts.

The investigations show that the struts will perform their design function even with the bushings dislocated; therefore, this condition is judged not to be reportable under either 10CFR50.55(e) or 10CFR21.

Yours very truly,

  1. fu A ' Y GLK:bb 8003190139 201 N. Market - Wachsta. Kansas - Mail Address: P.O. Box 208 / Wachsta. Kansas 67201 - Teleonone: Area Code (316) 261-6451