Forwards Interim Deficiency Rept Re Weld Deficiencies in Reactor Pressure Vessel Shield Wall
ML19305A805
Person / Time
Site: Hartsville Tennessee Valley Authority icon.png
Issue date: 03/13/1980
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19305A806 List:
References
NCR-HNP-A-087, NCR-HNP-A-87, NUDOCS 8003180372
Download: ML19305A805 (1)


Text

-

T, . ! ,

TENNESSEE VALLEY AUTHORITY CHATTANOOGA, TENNESSEE 374of 400 Chestnut Street Tower II March 13, 1980 -

Mr. James P. O'Reilly, Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Region II - Suite 3100 101 Marietta Street Atlanta, Georgia 30303

Dear Mr. O'Reilly:

HARTSVILLE NUCLEAR PLANT UNIT Al - REPORTABLE DEFICIENCY - RPV SHIELD WALL - WELD DEFICIENCIES (NCR HNP-A-087)

Initial report of the subject deficiency was made to R. W. Wright, NRC-0IE, Region II, on February 15, 1980. In coapliance with paragraph 50.55(e) of 10 CrR Part 50, we are enclosing the first interim report of the subject deficiency. TVA anticipates transmitting the final report on or before May 30, 1980. If you have any questions regarding this matter, please call Jim Domer at FTS 854-2014.

Ve y truly yours, TENNESSEE VALLEY AUTHORITY j &f ,, .

L. M. Mills, Manager",.