Metropolitan Edison Company (j

Post Office Box 542 Reading Pennsylvania 19603 215 929 3601 April 28,1979 GQL 0552 Director of Nuclear Reactor Regulation Attn: Brian K. Grimes, Assistant Director Engineering and Projects U.S. Nuclear Regulatory Commission Washington, D. C. 20555

Dear Sir:

Three Mile Island Nuclear Station, Unit I Operating License No. DPR-50 Docket No. 50-289 i

Radiological Effluent Technical Specifications On March 5, 1979, Met-Ed was granted an extension until April 15, 1979, for submitting the Draft Radiological Effluent Technical Specifications for Thr'se Mile Island Nuclear Station, Units 1 and 2.

On March 28, 1978, an incident occurred at Unit 2 which required, and continues to require, the support of nearly all available personnel. As a result we were unable to meet the April 15, 1979, due date. However, Met-Ed vill be able to submit the draft Radiological Effluent Technical Specifications and accompanying Offsite Dose Calculation Manual by July 15,1979 Therefore, Metropolitan Edison Company is requesting Cemission approval of a 90 day extension.

Your consideration in this matter is appreciated.

ncerely, v

J. G. Herbein Vice President Generation JGH:DGM:mrm cc: J. Collins H. Silver h