ML19303A589

From kanterella
Jump to navigation Jump to search

Letter to G. Couturequest for Additional Information Regarding Wec'S 2019 DFP Submittal
ML19303A589
Person / Time
Site: Westinghouse
Issue date: 11/15/2019
From: Maldonado Marilyn Diaz
NRC/NMSS/DFM/FFLB
To: Couture G
Westinghouse
MDiaz NMSS/DFM/FFL 415.7110
Shared Package
ML19303A587 List:
References
EPID L-2019-DFA-0004
Download: ML19303A589 (3)


Text

OFFICIAL USE ONLY - PROPRIETARY INFORMATION November 15, 2019 Mr. Gerard F. Couture Acting Licensing Manager Westinghouse Columbia Fuel Fabrication 5801 Bluff Road Hopkins, South Carolina 29061 -9121 USA

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION REGARDING WESTINGHOUSE ELECTRIC COMPANY LLC 2019 DECOMMISSIONING FUNDING PLAN UPDATE - ENTERPRISE PROJECT IDENTIFICATION NUMBER L-2019-DFA-0004.

Dear Mr. Couture:

By letter dated July 25, 2019 (Agencywide Documents Access and Management System (ADAMS) No. ML19206A043), Westinghouse Electric Company LLC submitted an updated decommissioning funding plan (DFP) as required by Section 70.25 of Title 10 of the Code of Federal Regulations (10 CFR), which requires Westinghouse to provide triennial updates to its DFP for its Columbia Fuel Fabrication Facility. The submission includes an updated decommissioning cost estimate and specifies that the licensee will provide executed financial assurance instruments after the U.S. Nuclear Regulatory Commission (NRC) review and approval of the cost estimate. Our review of your application has identified that additional information is needed before final action can be taken.

The additional information, specified in the enclosure, should be provided within 30 days from the date of this letter.

Pending your response, we anticipate completing our review by the end of February 2020. This date could change depending on the findings of our technical review, urgent assignments, or other factors. We will promptly communicate any significant changes to this schedule.

In accordance with 10 CFR 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRCs ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

This letter is decontrolled when separated from the enclosure.

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

OFFICIAL USE ONLY - PROPRIETARY INFORMATION G. Couture 2 If you have any questions regarding this communication, please contact me at 301-415-7110, or via e-mail to Marilyn.Diazmaldonado@nrc.gov.

Sincerely,

/RA/

Marilyn Diaz, Licensing Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 70-1151 License No. SNM-1107

Enclosure:

Request for Additional Information cc: KKline, NMSS westinghouse_ff@listmgr.nrc.gov

ML19303A587 (Pkg); ML19303A589 (Ltr); ML19303A591 (Encl.)

OFFICE NMSS/DFM/FFLB NMSS/DFM/FFLB NMSS/REFS/FAB NMSS/DFM/FFLB NAME MDiaz ELee KKline JIZimmerman DATE 11/06/2019 11/07/2019 11/13/2019 11/15/2019