Notice of Issuance of Directors Decision Under 10CFR2.206 Denying Seacoast Anti-Pollution League 790502 Request for Order to Show Cause Why CPs Should Not Be Suspended or Revoked
ML19296C860
Person / Time
Site: Seabrook  NextEra Energy icon.png
Issue date: 02/11/1980
From: Harold Denton
Office of Nuclear Reactor Regulation
To:
Shared Package
ML19296C848 List:
References
NUDOCS 8002280698
Download: ML19296C860 (2)


Text

-

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of

)

PUBLIC SERVICE COMPANY OF Docket Nos. 50-443 NEW HAMPSHIRE, et al.

)

50-444 (Seabrook Station, Unit Nos. I and 2)

)

NOTICE OF ISSUANCE OF DIRECTOR'S DECISION UNDER 10 CFR 42.206 By petition dated May 2,1979, Robert A. Backus, un behalf of the Seacoast Anti-Pollution League (SAPL) requested that the Director, Office of Nuclear Reactor Regulation, issue an Order to Show Cause why Construction Permit Nos.

CPPR-135 and CDPR-136 for the Seabrook Station, Unit Nos. I and 2, should not be suspended or revoked. SAPL based its request on:

(1) Failure of NRC to require development of an evacuation plan beyond the low population zone as part of the construction permit pro-ceedings, and (2) Failure of NRC to evaluate the consequences of a Class 9 accident, including the necessity for evacuation beyond the low population Zone.

Notice of receipt of SAPL's petition was published in the Federal Register (44 F. R. 32054 (June 4,1979)). On July 30, 1979, the New England Coalition on Nuclear Pollution (NECNP) filed a memorandum in support of SAPL's petition.

On November 16, 1979, the Commonwealth of Massachusetts also filed a memorandum in support. On October 12, 1979, the State of New Hampshire filed a Statement of Position.

'I 8002cggf[,

e

. Upon review of the material submitted by SAPL, NECNP, and Mas,achusetts and upon consideration of other relevant information, I have determined not to issue an Order to Show Cause. Accordingly, the requests of SAPL and NECNP are denied. A copy of the decision in this matter is available for inspection in the Commission's Public Document Room,1717 H Street, N. W., Washington, D. C. 20555, and in the local public document room for the Seabrook Station at the Exeter Public Library, Front Street, Exeter, New Hampshire 03883. A copy of this decision will also be filed with the Secretary for the Commission's review in accordance with 10 CFR 2.206(c) of the Commission's regulations.

As provided in 10 CFR 2.206(c), this decision will constitute the final action of the Commission 20 days after the date of issuance of the decision, unless the Commission on its own motion institutes a review of this decision within that time.

FOR THE NUCLEAR REGULATORY COMMISSION HSW Harold R. Denton, Director Office of Nuclear Reactor Regulation Dated at Bethesda, Maryland, this lith day of February 1980

.