Alabama Power Corrpany 600 Nor h leh Street Post OfSce Box 2641 Birmingham. Alabama 35291 Tetepnone 205 323-5341 F. L CLAYTON,.iR.
AlabamaPower Senor vice Presiaent the southem e'ecinc system February 7,1980 Docket No. 50-348 Director of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D.C.
20555 Attention:
Mr. Darrell G. Eisenhut
Dear Mr. Eisenhut:
FARLEY UNIT 1 FIRE PROTECTION PROGRAM MODIFICATIONS On December 12, 1979, a revised schedule for fire protection modifications for the Joseph M. Farley Nuclear Plant was submitted for your information. Subsequent to this referenced submittal, a reanalysis of the requirements contained in the Fire Protection Program Reevaluation was performed and the results compared to the status of Unit 1 modifications.
Based on this reanalysis, an updated schedule with explanatory notes is attached for your information and approval.
The revised schedule represents the date at which: the work involved will be completed; verification of compliance with applicable codes will be made; and any corrective action required will be performed.
If you have any questions, please advise.
Yours very truly, e
.t F. L. Clayton, Jr.
JDM/jd Attachments cc:
Mr. R. A. Thomas (O
Mr. G. F. Trowbridge
\\
80 0215 0 25 Ji'i
IMPLEMENTATION DATES FOR PROPOSED MODIFICATIONS (STATUS AS OF 2-5-80)
Item Date Unit 1 Unit 2
- 1. Sprinklers (All systems)
End of 2nd refueling Before fuel load outage Room 234, Area 16 Complete N/A l (1)
- 2. Yard Hydrants Complete N/A
- 3. Portable Extinguishers Complete Before fuel load
- 4. Hose Stations 2-29-80 Before fuel load l(2)
- 5. Smoke Detectors 9-1-80 9-1-80 l(3)(4)
- 6. UL Rated Doors 4-15-80 Before fuel load
- 7. Fenetration Seals 9-1-80 Before fuel load
- 8. Portable Smoke Removal 3-31-80 N/A (5)
- 9. Term. Cabinet Complete Before fuel load Water Protection
- 10. Damper Rework End of 2nd refueling Before fuel load outage
- 11. Eight-Hour Battery Complete Before fuel load Packs
- 12. Hose Stations in CTMT Complete Before fuel load
- 13. RCP Oil Collection End of 2nd refueling Before fuel load outage
- 14. Fire Pump Barriers Complete N/A
- 15. DG Pot. Transfo rmer Complete' Complete c'rcuit
- 16. Barriers 9-1-80 9-1-80
- 17. Inside Water Supply 3-15-80 Before fuel load (6)
. Item Date Unit 1 Unit 2
- 18. HSP Switch Relocation End of 2nd refueling Before fuel load outage
- 19. HSP Instrument Mods.
End of 2nd refueling Before fuel load outage
- 20. Barriers in S.W.
Complete Complete Structure
- 21. Firenroof Control Complete N/A Room Kitchen
- 22. Modify New Fuel End of 2nd refueling N/A Storage Racks outage NOTES:
- 1. This system is complete and is operable manually.
- 2. Complete except for two (2) stations to be installed at the Service Water Building.
- 3. Complete except for one (1) steel hatch plate to be replaced with door.
Eight (8) week delivery required.
- 4. NRC Safety Evaluation required door between room 471 and room 2432, and double doors leading outside from room 474 to be fire rated. These doors provide pressure and security boundaries. APCo is presently pursuing a method of qualifying security doors for fire rating, but at this time no evidence of this dual qualification capability has been obtained.
- 5. Equipment is purchased and on site available for use.
Metal enclosures are being fabricated in order to provide permanent location of the units.
- 6. Complete except for control circuit modifications on two (2) motor operated valves.