Text
a \\ '-?
Y lc
%,p,j UNITED STATES
[
NUCLEAR REGULATORY COMMISSION s
q y D y, f
W ASHINGTON, D.C. 20555 A
@I.O G g ^..:
-8) n
~J
/<'
uame
%v f gg 4 G30 ;.
7 OFFICE OF THE March 4,1980 Off-b cf 23 S:m.y h0dd.y 0 [p,j3 SECRETARY N
En :':
lao f,
M lJ \\
Terence H. Benbow, Esq.
William B. Reynolds, Esq.
Steven A. Berger, Esq.
Robert E. Zahler, Esq.
Winthrop, Stimson, Putnam Shaw, Pittman, Potts and Trowbridge and Roberts 1800 M Street, N. W.
40 Wall Sireet Washington, D. C.
20036 New York, New York 10005 Lee A. Rau, Esq.
Joseph A. Rieser, Jr., Esq.
Reed, Smith, Shaw and McClay 1150 Connecticut Avenue, N.W.
Washington, D. C.
20036 In the Matter of THE TOLED0 EDIS0N COMPANY and THE CLEVELAND ELECTRIC ILLUMINATING COMPANY (Davis Besse Nuclear Power Station, Units 1, 2 and 3)
Docket Nos. 50-346A 50-500A 50-501A THE CLEVELAND ELECTRIC ILLUMINATING COMPANY, ET AL.
(Perry Nuclear Power Plants, Units l'and 2)
Docket Nos. 50-440A 50-441A Gentlemen:
On February 15, 1980, the Commission extended the time for consideration of petitions to review the decision of the Atomic Safety and Licensing Appeal Board (ALAB-560) in the subject case.
That time period has now elapsed without the Commission granting the petition in whole or in part.
Accordingly, the petition is deemed
.nied as rovided in 10 CFR 2.786(b)(5).
t 5
- cerely, hA*
Samuel J.
JQlk Secretary of the Commissi n L
cc:
Service List 8003070