ND-19-1258, Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.5.02.08b.i (Index Number 542)

From kanterella
(Redirected from ML19290H171)
Jump to navigation Jump to search
Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.5.02.08b.i (Index Number 542)
ML19290H171
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 10/17/2019
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ITAAC 2.5.02.08b.i, ND-19-1258
Download: ML19290H171 (6)


Text

Michael J. Yox 7825 River Road Sk.Southern Nuclear Regulatory Affairs Director Vogtle 3 & 4 Waynesboro, GA 30830 706-848-6459 tel OCT 1 7 2019 Docket Nos.: 52-026 ND-19-1258 10 CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.5.02.08b.i [Index Number 5421 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of October 11, 2019, Vogtle Electric Generating Plant(VEGP) Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.5.02.08b.i [Index Number 542] has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEI-08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed.

All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant(VEGP) Unit 4 Completion Plan for Uncompleted ITAAC 2.5.02.08b.i [Index Number 542]

MJY/SBB/sfr

U.S. Nuclear Regulatory Commission ND-19-1258 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III (w/o enclosures)

Mr. D. L. McKinney (w/o enclosures)

Mr. M. D. Meier (w/o enclosures)

Mr. D. H. Jones (w/o enclosures)

Mr. G. Chick Mr. M. Page Mr. M. J. Yox Mr. A. S. Parton Ms. K. A. Roberts Mr. T. G. Petrak Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reoulatorv Commission Mr. W.Jones(w/o enclosures)

Mr. F. D. Brown Mr. C. P. Patel Mr. G. J. Khouri Ms. S. E. Temple Mr. N. D. Karlovich Mr. A. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. V. Hall Mr. G. Armstrong Ms. T. Lamb Mr. M. Webb Mr. T. Fredette Mr. C. Weber Mr. S. Smith Oqlethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen

U.S. Nuclear Regulatory Commission ND-19-1258 Page 3 of 3 Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Dalton Utilities Mr. T. Bundros Westinqhouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. C. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. J. E. Hosier, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Balch Bingham

U.S. Nuclear Regulatory Commission ND-19-1258 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-19-1258 Enclosure Vogtle Electric Generating Plant(VEGP) Unit 4 Completion Plan for Uncompleted ITAAC 2.5.02.08b.i [Index Number 542]

U.S. Nuclear Regulatory Commission ND-19-1258 Enclosure Page 2 of 3 ITAAC Statement Design Commitment 8.b) The RMS provides for the transfer of control capability from the MCR to the RSW using multiple transfer switches. Each individual transfer switch is associated with only a single safety-related group or with non-safety-related control capability.

Inspections/Tests/Analvses i) An inspection will be performed to verify that a transfer switch exists for each safety-related division and the nonsafety-related control capability.

Acceptance Criteria i) A transfer switch exists for each safety-related division and the nonsafety-related control capability.

ITAAC Completion Description Multiple ITAAC are performed to ensure that the Protection and Safety Monitoring System (PMS) provides for the transfer of control capability from the Main Control Room (MCR)to the Remote Shutdown Workstation(RSW) using multiple transfer switches. Each individual transfer switch is associated with only a single safety-related group or with non-safety-related control capability. The subject ITAAC requires that an inspection be performed to verify that a transfer switch exists for each safety-related division and the non-safety-related control capability.

The PMS and Plant Control System (PLS)transfer switches are installed in accordance with approved drawings and specifications released by engineering for construction. An inspection is performed to verify that a transfer switch exists for each safety-related division and the non safety-related control capability. The inspection is performed in accordance with Inspection Procedure XXX (Reference 1), which requires performance of visual observations to compare the installed equipment to the approved drawings. The inspection results are documented in the Principal Closure Document XXX (Reference 2) supporting the ITAAC 2.5.02.08b.i Completion Package (Reference 3) and confirm that a transfer switch exists for each safety related division and the non-safety-related control capability.

Principal Closure Document XXX is available for NRC inspection as part of the ITAAC 2.5.02.08b.i Completion Package.

List of ITAAC Findings In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company(SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

U.S. Nuclear Regulatory Commission ND-19-1258 Enclosure Page 3 of 3 References ^available for NRG inspection)

1. Inspection Procedure XXX
2. Principal Closure Document XXX
3. ITAAC 2.5.02.08b.i Completion Package
4. NEI 08-01,"Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"