Text
,
i t
Tube Turns Division I-of Chemetron Corporation l
N0 RICE OF DEVIATION g'
Based on the results of an NRC inspection conducted on December 3-7, 1979, it,.
appears that one of your activities was not conducted in accordance with NRC requirements.
/
,f Criterion V of Appendix B to 10 CFR 50 states:
,,Y
" Activities affecting quality shall be prescribed by docuqented' instructions, procedures, or drawings, of a type appropriate t6 the circumstances and shall be accomplished in accordance! wity; these instructions, procedures, or drawings.
Instructions, pro "
cedure-, or drawings shall include appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfactorily accomplished."
The deviation from these requirements is as follows:
The QA Manual Procedure TT22-333, Revision 1, paragraph 3.2, states in part, "The Production Superintendent and Foreman over the welding operations chall be responsible for:
Observing that welding operations are performed to and within the parameters established by the welding pro-cedure:
Contrary to the above, the welding being performed in the manufacture of a guard pipe subassembly for a main steam penetration on Tube Turns Order-Item 070195-001 was not accomplished in accordance with welding procedure TT12-0114, Revision 0, as required by the Manufacturing Order (routing) No. 070195-001 Procedure Actual TT12-0114 Values Revision 0 Use d Range Amperage Range, Amps -
220-280 320 Torch Gas Flow, CFH -
36-45 31 8003399 yf