ML19290C552

From kanterella
Jump to navigation Jump to search
QA Program Insp Rept 99900061/79-02 on 791018.No Noncompliance Noted.Major Areas Inspected:Vendor Corrective Action on Identified Problems of Cracked Hardfacing of Gate Valve Disc & Sheared Pin of Swing Check Valve
ML19290C552
Person / Time
Issue date: 11/28/1979
From: Kelley W, Whitesell D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19290C548 List:
References
REF-QA-99900061 99900061-79-2, NUDOCS 8001220077
Download: ML19290C552 (7)


Text

_... _.

U. S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT REGION IV Report No.

99900061/79-02 Program No. 51300 Company:

Velan Engineering Ltd.

2125 Ward Avenue Montreal, Quebec, H4M IT6, Canada Inspection Conducted:

October 18, 1979 Inspector:

b 0,b

(

,L w

(

U h

Wm'. D. Kelley,Tontr2 ct'or Inspect'dr Date ComponentsSection I Vendor Inspection Branch Approved by:

f job x

t as:=

(N 4 t_(

D.E.Whitesell', Chief A

Ddte ~

ComponentsSection I Vendor Inspection Branch Summary Inspection on October 18, 1979 (99900061/79-02)

Areas Inspected:

Implementation of 10 CFR 50, Appendix B and applicable codes and standards including, vendor's corrective action on identiff.:d problems of cracked hardfacing of gate valve disc and sheared pin of swing check valve.

The inspection involved six (6) inspector-hours on site by one (1) NRC inspector.

Results:

In the one (1) area inspected, no deviations or unresolved items were identified.

1788 008 8001220 07 2

2 DETAILS A.

Persons Contacted Velan Engineering, Ltd. (VEL)

  • J. M. Farrell, Corporate Manager of Engineering A. Nartini, QA Administrator
  • Denotes these person who attended the Exit Interview (See paragraph D)

B.

General Review of Vendor's Activities 1.

There has been no change of the status of the ASME Certificate of Authorization, the authorized inspection agency, or the authorized nuclear inspector as reported in Report Number 99900061/79-01.

2.

VEL is doing all the design, design drawings, design reports and stress analyses for the orders placed at Velan Valve Corporation (VVC), Burlington, Vermont.

3.

VEL is manufacturing all of its nuclear valve orders for the United States market at the VVC plant in Burlington, Vermont.

C.

Follow-Up of Reported Deficiencies 1.

Cracked Hardfacing of Gate Valve Wedges a.

Background Information On July 17, 1979, the Tennessee Valley Authority (TVA), phoned NRC-IE-RII, to report that during the inspection of the safety injection system at Sequoyah Plant 1, cracks had been identified in the hardfacing wedges in two gate valves located in the accumulator charging line. The valves had been manufactured by Velan Engineering Ltd. (VEL).

b.

Objectives The objectives of this area of the inspection aere to ascertain whether this problem might be generic to plants other than Sequoyah, and whether the safety significance had been eval-uated to determine whether the defect was reportable under 10 CFR 21.

I788 009

3 c.

Method of Accomplishment The foregoing objectives were accompliched by:

(1) Review of the customer's procurement documents as follows:

(a) Purchase Order Number 54-CAK-91710BN, dated December 23, 1969.

(b) Equipment Specification Number G676258, " Motor Operated Valves," dated May 23, 1966; Revision 1, dated October 23, 1968.

(c) Quality Assurance Specification Number QC-SI, dated January 2, 1970.

To ascertain the number, sizes, quality class of the valves, and the design criteria i.e. pressure, tempera-ture, materials, and governing codes and standards spec-ified in the procurement documents.

(2) Review of VEL's PO Number 3383, to verify w' ther'all of the pertinent quality requirements of the customer's procurement documents had been included.

(3) Review of VEL's Safety Report issued in June 1973, j

directing the attention of not only its customers, but the nuclear industry, to the fact that fast closing valve l

operaters, have the potential to damage valve parts and the valve operator by overstresses generated by stalled motor torque due to the time delay between tripping the switch and motor shutoff.

Revision 1, dated October 1973, included VEL's Test Report Number RD-014/1, " Strain Gage Test on 1" - 1500# BB Gate Valve Wedge" which demonstrated that repeated over torquing the valve wedge results in cracking the stellite surface.

(4) Review of VEL Engineering Calculations No. RD-115, Revision 0; " Evaluation Report - 8 inch and 10 inch Wedges" for Pacific Gas and Electric, Diablo Canyon.

(5) Review of VEL Engineering Calculations

" Cast Wedges" dated January 9, 1973.

(6) VEL Engineering Calculations, " Forged Wedges 10", dated August 1, 1978.

(7) Inspected the photomicrograph of a CF8 Stainless Steel Wedge, hardfaced with stellite No. 6; and 1788 Od

4 (8) Discussions with the cognizant managers concerning the following information:

(a) Evaluation of the cause.

(b) The corrective action taken and/or proposed.

(c) The generic aspects of the problem.

(d) Evaluation of the safety significance under 10 CFR 21.

d.

Findings It appears that the VEL motor operated valves were designed and manufactured in compliance with the customer's purchase order and design specification. However, the sizing and selection of the valve actuator was done before the effects of stalled motor torque and fast closing speeds were known.

Early in 1973, VEL's management became concerned regarding the increasing reports of plants shutting down due to valve problems, and also pressures coming from its engineering department relative to the lack of certain technical infor-mation concerning the actual torque and forces generated by fast acting operators with motors capable of functioning at 70% rated power. These concerns prompted VEL into pub-lishing a Safety Report covering its concerns and the lack of technical information to enable the appropriate engineers to select actuators the best suited for the valves' speci-fied function.

One of the major concerns of VEL was the ever increasing demands by its customer for faster closing speeds, and actuator motors suitable for low voltage operation (70%).

To provide adequate technical information VEL performed a series of tc Ls which not only provided pertinent technical information, but also confirmed VEL's concerns that the speed vs. torque thrust could overstress valve and operator parts to destruction.

From the results of these tests together with updated infor-mation from Limitorque Corp. (LC) who also had been per-forming research and development testing, VEL revised its Safety Report to include several of its test results, in October 1973. The revised Safety Report was issued to all of its nuclear customers, and the nuclear' industry as a whole.

1788 011

5 The test results together with the calculations enabled VEL determine that the hardface cracking problem only existed in 8 and 10 inch gate valves, with cast steel wedges, and a specified closure time of ten seconds or less.

e.

Generic Impact

..ast valves order prior to 1971 were specified to meet the requirements el ASA 16.5.

In many instances the customer's P0 covered valves for several facilities, and VEL was not provided with any shipping instructions until the valves were inspected and accepted by the customer. At which time the customer signed the Quality Release Forms (QRF) and identified the facility to which the valves identified there on were to be shipped. QRF was then filed under the serial number (s) of the valve (s) identified on the QRF.

The retrievel 'of QRF for the valves purchased by the cus-tomer's PO number 54-CAK-91710BN indicates that the only 8 and 10 inch cast wedge gate valves with a specified closure time of 10 seconds or less was shipped to the Sequoyah Nuclear Plant, and Diablo Canyon Plant.

f.

Corrective Action It appearc that VEL initiated its initial corrective action in October 1973, with the issuance of its Safety Report to all of its customers, concerning the potential damage to valve and actuator parts due to overstressing that can be generated by the stalled motor torque of high speed actuators.

The Safety Report also provided specific instructions con-cerning the precautions the customer ~ should follow to negate or minimize these potential dangers.

The cast steel wedges in the 8 and 10 inch valves with specified closure time of 10 seconds or less, supplied in compliance with P0 No. 54-CAK-91710BN, has been replaced by VEL, with forged steel wedges of a heavier design.

Since 1973 additional technical information concerning the magnitude of stalled motor torque, the lag time between the switch disconnect and motor drop-out, the relation of the actuator's efficiency to RPM output, and new torque sensors and compensating units have been developed to absorb the torque and reduce the resulting stresses. Also the new information provides the design engineer with more reliable and precise data which enables him to more accurately 1788 012

s 4

6 evaluate the actual stress that will be imposed on various parts of the valve to determine the adequacy of the design to resist those stresses.

It also provides better and more reliable information to size and select actuators with motors and gearing most suitable for its function with minimum adverse operating effects.

2.

Sheared Pin on Valve Disc a.

Background Information NRC RII received a letter from the Tennessee Valley Authority dated December 29, 1978 that reported during refueling outage on Diowns Ferry Nuclear Plant, Unit 1, the 10 inch, 150 pound carbon steel swing check valve 1-71-580 in the RCIC system failed the local leak rate test. During the maintenance inspection the valve was found in an open pc. ' tion due to the pin shearing on the valve disc. A new plu and disc were installed and the valve passed the leak test satisfactorily.

TVA stated in their report that this was the first failure of this nature and they considered it an isolated case and planned no recurrence control action.

b.

Objective The objective of this area of the inspection was to ascer-tain:

(1) Whether the vendor had evaluated the cause of pin failure on the valve disc and had evaluated the safety significance of the problem in conformance with their procedure for evaluating the report-ability of defects in accordance with 10 CFR 21.

Also, (2) The generic implications of this problem, and (3) Whether the corrective action that was taken, or to be taken, is appropriate.

c.

Method of Accomplishment The foregoing objectives were accomplished by a discussion with the corporate manager of engineering at the VEL corporate office at Montreal, Quebec, Canada, on October 18, 1979, and by a telephone conference on October 26, 1979.

i

~

l 1788 013 i

7 d.

Findings (1) From the discussions with the corporate manager of engineering, tL e following was determined.

(a) The pin referenced in the TVA report is actually part of the cast steel disc.

(b) TVA is performing an analysis of the system to determine the safety significance of the valve failure and to verify what the dynamic impact loading on the disc would be when the steam flow opens the valve.

(c) VEL is orforming a stress analysis to determine m

the system fluid velocity necessary for disc pin failure.

(d) TVA is retaining the disc parts; therfore, VEL is unable to perform an examination of the parts to ascertain the nature and/or cause of the pin failure.

(2) Within this area of the inspection no deviations or unresolved items were identified.

e.

Generic Impact The generic impact cannot be determined until the TVA and VEL analysis are completed and compared with the results of the examination of the failed parts.

f.

Corrective Action l

The corrective action will be reviewed on a subsequent inspection after the TVA and VEL anal-rsis are complete and compared with results of the examination of the failed parts.

D.

Exit Interview At the conclusion of the special inspection on October 18, 1979, the i

inspector met with the company's management, identified in paragraph A, for the purpose of informing as to the results of the inspection.

During this meeting management was informed no deviations or unresolved items were ident '" ad.

The company's maur t acknowledged the inspector's statement and had no comments.

1788 014