Responds to IE Bulletin 79-14 Re Seismic Analysis for safety-related Piping Sys.Insp for as-built Configurations Inappropriate Until Sys Piping Completed
ML19290B870
Person / Time
Site: Hope Creek  PSEG icon.png
Issue date: 11/05/1979
From: Martin T
Public Service Enterprise Group
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
IEB-79-14, NUDOCS 7912140289
Download: ML19290B870 (1)


Text

Yk Thomas J. Martin Public Service Electric and Gas Company 80 Park Place Newark, N.J. 07101 201/430-8316 Vice President Engineering and Construction g7 Mr. Boyce H.

Grier, Director Office of Inspection and Enforcement U.S.

Nuclear Regulatory Commission Region 1 631 Park Avenue King of Prussia, Pennsylvania 19406

Dear Mr. Grier:

NRC IE BULLETIN NO. 79-14 SEISMIC ANALYSIS FOR AS-BUILT SAFETY-RELATED PIPING SYSTEMS NO. 1 AND 2 UNITS HOPE CREEK GENERATING STATION In our reply to IE Bulletin No. 79-14 dated November 1,

1979, a word was inadvertently omitted which changes the context of the letter.

The first paragraph of the letter should read as follows:

The NRC requires that we inspect all of Hope Creek Generating Station's Units No. I and 2 safety related systems in action items 2 and 3.

Due to the small amount of piping and hangers installed and the lack of any piping systems completed, a special inspection for "as-built" configurations would not be appropriate until the system piping is completed.

Should additional information be desired, we will be pleased to further discuss it with you.

Very truly yours, CC:

Office of Inspection and Enforcement

}g

}kh Division of Reactor Construction Inspection Washington, D.C.

7 912140 c) b h