ML19289D022
| ML19289D022 | |
| Person / Time | |
|---|---|
| Site: | Hatch |
| Issue date: | 12/29/1978 |
| From: | Staffa R GEORGIA POWER CO. |
| To: | Long F NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| Shared Package | |
| ML19289D017 | List: |
| References | |
| NUDOCS 7901290121 | |
| Download: ML19289D022 (3) | |
Text
Georgia Power Corm,pany 230 PeaMeee Street Post Ottice Box 4545 At;anta Gerg a 30303 Tetepnone 404 522-6060 i' a n.
.... v u l, 1.'0 '.m m
Power Supply Engineer 6ng and Serv 6ces J d[.k$ehembhr)I9,h78 Georgia Power c.
.e.~
United States Nuclear Regulatory Commission Office of Inspection and Enforcement
REFERENCE:
Region II - Suite 1217 RII: HDJ 101 Marietta Street 50-366/78-44 Atlanta, Georgia 30303 ATTENTION:
Mr. F. J. Long Gentlemen:
The Georgia Power Company wishes to submit the following information in response to the seven apparent items of noncomplianca identified in the above referenced inspection report.
The A.
This item referred to the lack of control of special processes.
weld on the seismic class 1 hanger was cut out and a new weld made utilizing the proper procedure. The welding materials procedure HNP-6916 has been revised to add more stringent controls of welding rods including location of the actual weld.
This item referred to an insufficient calibration program for limiting B.
conditions of operation (LCO) instruments. The problem had been identified prior to the NRC inspection by plant personnel and correc-tive action was in progress. However, because the corrective action had not been documented in written form, such as maintenance requests and Deviation Reports, it was considered to be an item of noncompliance.
The LCO instrument calibration program has been revised and all instru-mentation calibrations are currently up to date.
Also reported under this same item of noncompliance was the failure of laboratory personnel to document the due date and recalibration frequency of two spectrophotometers. The required due dates and calibration frequencies have been established completing the necessary corrective action.
C.
This item referred to either the lack of procedures or inadequate procedures addressing all of the specific qualitative and quantitative acceptance criteria required by ANS1 Standards N45.2.3 " Housekeeping".
N4 5. 2. ll " Design", N45. 2.12 "Audi ting", and N45. 2.13 " Procurement" as coc=11tted to in the accepted Quality Assurance Program.
N4 5.2.3 " Housekeeping" commitment is addressed on page A.l.39-1 of the Hatch Unit 2 FSAR.
In lieu of designating cleanliness zones as required by N45.2.3, Plant Hatch will implement housekeeping controls commensurate with paragraph 5.2.10 of ANS1 N18.7-1976 through the radiatien protection and security procedures. The FSAR is being revised to reflect this 1 1979.
approach and should be completed by mad 0,12So);;q
'19603
GeorgiaPbwer d U. S. Nuclear Regulatory Commission ATTN:
Mr. F. J. Long Page Two December 29, 1978 N45.2.11 " Design" and N45.2.13 " Procurement" requirements for description of the interface controls will be described in the Plant Hatch QA Manual, with each organization performing safety related design and pro-curement activities required to have procedures which implement N45.2.11 and N45.2.13, respectively. All QA Manual and procedure revisions are scheduled for completion by March 1, 1979, except the plant procedure for design which will not be complete until April 1, 1979.
N45.2.12 " Auditing" standard committed to in the Hatch Unit 2 FSAR was Draft 3 Revision 4.
Subsequent to acceptance of the FSAR by Nuclear Reactor Regulation ANSI N45.2.12-1977 was issued.
The Hatch Unit 2 FSAR is being revised to commit to ANSI N45.2.12-1977 and the appropriate procedures will be revised to implement those requirements.
The schedule for completion'is March 1, 1979.
D.
This item referred to conditions adverse to quality which had not been promptly corrected. Plant management had identified this problem prior the the NRC inspection. The QA site audit procedure is being revised to include specific time limits for response to audit findings and the plant procedure is now being fully implemented. The schedule for imple-mentation is March 1, 1979.
E.
This item referred to the authorities and duties of all organizations within and outside of the Georgia Power Company that are involved in both the procurement and design activities were not clearly established and delineated in writinR. The Plant Hatch Quality Assurance Manual vill describe the responsibilities and interface controls, and the QA Manual will reference the applicable implementing procedures. All QA Manual and procedure revisions are scheduled for completion March 1, 1979.
F.
This item referred to sufficient records not being maintained to furnish evidence of activities affecting quality nor the results of certain reviews in three areas:
1.
The required review of deficient items every 90 days is not documented.
2.
The required review of QAFR file folders every 30 days is not documented.
3.
The type of lubricant used when changing and/or adding same to components is not recorded.
GeorgiaPbwer d U. S. Nuclear Regulatory Commission ATTN:
Mr. F. J. Long Page Three December 29, 1978
/
The documention of the reviews in items 1 and 2 is now being accom-plished. No further action is required.
In item 3 the control and traceability of consumables used in the maintenance of safety related equipment is being evaluated.
Interim administrative controls will be developed and implemented by January 15, 1979, with permanent controls established by July 26, 1979.
C.
This item referred to the results of audits not being properly documented and reviewed by management in accordance with the re-quirements of the accepted QA Program.
The procedures controlling this activity are being revised and should be completed by March 1, 1979.
e This inspection report contains no information which is believed to be proprietary. If you have any questions or comments, please contact my office.
Very truly yours, l
c~
Q Jt. W. S ffa, Manage of Qua ity Assurance DRS/mb