public service company oe cdorade P. O. Box 361, Platteville, Colorado 80651 February 20, 1979 Fort S t.
Vrain Unit No. 1 P-79047 Mr. Karl V. Seyfrit, Dire ctor Nuclear Regulatory Commission Region IV Office of Inspection and Enforcement 611 Ryan Plaza Drive Suite 1000 Arlington, Texas 76012 REF:
Facility Operating License No. DP R-34 Docket No. 50-267
Dear Mr. Seyfrit:
Enclosed please find a copy of the ninth Startup Report for Fort St.
Vrain Nuclear Generating Station, Unit No. 1.
This report covers the period from Augus t 22, 1978 through November 22, 1978, and is sub-mitted in fulfillment of the requirements of Section 7.5.la of the Fo rt S t. Vrain Technical Specifications.
Very truly yours, Do Wa Manager, Nuclear Production DW/alk cc:
Director, I and E Director, MIPC 35
% i 7902260305
THE FORT ST. VRAIN INITIAL APPROACH TO POWER TESTS (B-SERIES)
INTERIM REPORT 9 Report for Period Ending November 22, 1978
, Interim Report 8 covering the 90 day period ending August 22, 1978, reported the completion of all tests up to 70% of plant load. Since the Nuclear Regulatory Commission did not release the plant for operation at power levels in excess of 70%, no further Initial Approach to Power Tests were performed during the 90 days ending November 22, 1979.
Future interim reports will report the results of any s tartup tes ts.
@