Ack Receipt of NRC 790131 Ltr.Util Feels Any Design & Initial Const Scheduled to Occur Between Now & 791101 Can Proceed W/O Precluding Possible Addition of ATWS Mitigating Equipment
ML19283B575
Person / Time
Site: 05000580, 05000581
Issue date: 02/16/1979
From: Mcwhorter R
OHIO EDISON CO.
To: Baer R
Office of Nuclear Reactor Regulation
References
NUDOCS 7902260291
Download: ML19283B575 (2)


Text

o e

O ROBERT J. McWHORTER OHIO EDISON COMPANY 76 SOUTH MAIN STREET, AKRON, OHlo 44308 e 216-384-5918 vice m.iour February 16, 1979 Mr. Robert Baer Chief, Light Water Reactors Branch No. 2 Division Project Management U. S. Nuclear Regulatory Commission Washington, D. C. 20555

Subject:

Eric Nuclear Plant, Units 1 & 2 Docket Nos. SIN 50-580 & STN50-581 Anticipated Transients Without Scram

References:

1. NUREG-0460, Volume 3, December 1978.
2. Letter, R. L. Baer (USNRC) to R. J. McWhorter (OEC),

Dated January 31, 1979.

Dear Mr. Baer:

Ohio Edison has reviewed your letter of January 31, 1979 (Reference 2) with our NSSS supplier, Babcock and Wilcox Company, and our A/E, Gilbert / Commonwealth Associates, Inc. Based upon our current understanding of the NRC's request, it is our position that any design and initial construction of the Eric Plant scheduled to occur between now and November 1, 1979, can proceed without precluding the addition of ATWS mitigating equipment, as outlined in References 1 and 2 above.

However, it should be noted that the final detailed requirements of the NRC are not known at this time, but will be established by November 1, 1979 (Reference 1). When these regulatory requirements have been finally established, Ohio Edison will determine what, if any, design modifications are needed for Eric Nuclear Plant.

Should the NRC increase its requirements for the mitigation of ATWS beyond those specified in References 1 and 2 above, for B&W plants, or should the NRC final rule / regulations on ATWS be issued after November 1, 1979, Ohio Edison cannot assure that the design and initial construction of Erie Plant would be such so as not to preclude their addition.

790226029[

" Mr. Robert Baer February 16, 1979 If you need additional information or clarification, please advise.

Very truly yours,

/8 i%6 ./tu? b d<tC' RJM/JAll:vrm cc: TAKayuha WEKessler GCharnoff A11 Lazar EStebbins RTufts RWebb