ML19282D607

From kanterella
Jump to navigation Jump to search
Presentation of Experiences of Simplified Safety Evaluation Report Common Q Platform Pilot Project
ML19282D607
Person / Time
Issue date: 10/09/2019
From: Richard Stattel
NRC/NRR/DE/EICB
To:
Richard Stattel 415-8472
References
Download: ML19282D607 (8)


Text

Experience from Simplified Safety Evaluation Report Common Q Platform Pilot Project Richard Stattel.

Sr. Electronics Engineer, Instrumentation & Controls Branch, Office of Nuclear Reactor Regulation, US Nuclear Regulatory Commission

Common Q Platform

  • TR Approved - 2000
  • Calvert PAMS - 2003
  • Palo Verde CPC - 2003
  • TR Updated - 2013
  • TR Revision 4 - 2019 TR Simplified Review Schedule:
  • Application for review received (June 2019)
  • Supplement 1 - Summary of changes (July 2019)
  • Supplement 2 - CPU Load Change (August 2019)
  • Supplement 3 - Equipment Qualification Report (September 2019)
  • Draft SE complete (October 2019) 2

Common Q Platform Qualifying Aspects of Common Q TR for Simplified Review Process

  • The Common Q Platform was previously approved.
  • WDT Changes being made were known to the NRC due to previous operability reviews conducted in 2017 and 2018.
  • Additional changes to TR were considered to be minor.
  • A new module addition to platform - DI621
  • Equipment Qualification Test Results for new module to be provided
  • Other minor report corrections and clarifications to be made.
  • The NRC did not expect the changes to affect any of the TR safety conclusions or methods of evaluation.

3

Common Q Platform 4

Common Q Platform 5

Common Q Platform Unanticipated Complications Discovered During TR Review

  • A new operating system for the FPDS was being introduced to the platform.
  • Instead of a single module (DI621), the TR and test report included an additional 16 modules.
  • The TR change also added 7 new modules that had not undergone complete equipment qualification.
  • Westinghouse requested a revision to the method of making setpoint and configuration changes to the system during plant operations.

6

Lessons Learned Summary

  • Though we were able to perform the evaluation using the simplified review process, several of the issues discovered during the review could have pushed the evaluation out of the process.
  • If the applicant had persisted in requesting the method change, the evaluation would have required RAIs and would have been extended significantly.
  • The NRC could have limited its review to the original anticipated project scope but this would likely have resulted in a subsequent second submittal.

7

End of Presentation Questions 8