UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 October 9, 2019 Mr. Don Moul Vice President, Nuclear Division and Chief Nuclear Officer Florida Power & Light Company Mail Stop: NT3/JW 15430 Endeavor Drive Jupiter, FL 33478
SUBJECT:
REQUALIFICATION PROGRAM INSPECTION - TURKEY POINT NUCLEAR PLANT UNITS 3 AND 4
Dear Mr. Moul:
In a telephone conversation on October 7, 2019, Mr. Mark Bates, Senior Operations Engineer, and Mr. Mark Wilson, Supervisor Licensed Operator Requalification Training, made arrangements for the NRC to inspect the licensed operator requalification program at Turkey Point Nuclear Plant Units 3 & 4. The inspection is planned for the week of December 2, 2019, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program. It is our understanding that you have committed to maintain your plant-referenced simulator in accordance with ANSI/ANS-3.5-2009, American National Standard for Nuclear Power Plant Simulators for Use in Operator Training and Examination, and that you have also committed to ANSI/ANS-3.4-1983, Medical Certification and Monitoring of Personnel Requiring Operator Licenses for Nuclear Power Plants.
In accordance with 10 CFR 55.59, the NRC has requested that you submit the material by the due dates specified in paragraph A of the Enclosure, in order to support the NRC's in-office inspection program needs. The NRC has further requested that you have all items as specified in paragraph B of the Enclosure available for review for the inspectors on the first day they arrive on site. Mr. Wilson has been advised of this request and provided with the name and address of the NRC lead inspector assigned to this inspection.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number Part 55 (3150-0018)
D. Moul 2
The public reporting burden for this collection of information is estimated to average 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission,Washington, DC 20555-0001, or by Internet electronic mail at infocollectsresource@nrc.gov; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0101), Office of Management and Budget, Washington, DC 20503.
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB approval number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. (The Public Electronic Reading Room).
Thank you for your cooperation in this matter. If you have any questions regarding this inspection please contact Mr. Mark Bates at (404) 997-4612, (Internet E-mail:
Mark.Bates@nrc.gov), or me at (404) 997-4551, (Internet E-mail: Gerald.McCoy@nrc.gov).
Sincerely,
/RA/
Gerald J. McCoy, Chief Operations Branch 1 Division of Reactor Safety Docket Nos.: 50-250, 50-251 License Nos.: DPR-31, DPR-41
Enclosure:
Materials Request List cc: Distribution via Listserv
ML19282C748 SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII/DRS RII/DRS NAME MBates GMcCoy DATE 10/9/2019 10/9/2019
Enclosure Materials Request List The items listed below are necessary to support the Licensed Operator Requalification Program Inspection (IP-71111.11) in December 2019 at the Turkey Point Nuclear Plant. Items listed under In-office inspection material must be received in the NRC Region II office by the due dates specified below. Items listed under On-site inspection material should be ready for review upon arrival of the inspectors on December 2, 2019.
A.
In-office inspection material:
- 1. List of all licensed individuals (active and inactive; RO and SRO) including license restrictions. [November 12, 2019]
- 2. Organizational Chart for the training department, including the simulator fidelity staff, with phone number/email contact information. [November 12, 2019]
- 3. Weekly examination schedules for the weeks that the 2019 annual operating exams will be administered, including a list of personnel scheduled for testing the week of December 2, 2019. [November 12, 2019]
- 4. All 2019 biennial written examinations that have been approved for administration, final answer keys, re-take examinations, and spreadsheets or outlines that show the usage of written examination questions on the different versions of these written examinations.
[As available on November 12, 2019 or following completion of the biennial written examinations] (exam security related item)
- 5. Site procedure(s) governing the conduct (process and content) of license operator requalification training (classroom & simulator), examination development/administration, remedial training, and examination security. [November 12, 2019]
- 6. Site procedure(s) governing simulator configuration control, maintenance, and fidelity testing methods used to fulfill ANSI/ANS 3.5-2009 requirements. [November 12, 2019]
- 7. All JPMs that have been approved for administration, including spreadsheets or outlines that show the usage of the JPMs in all of the 2019 annual exam weeks. [As available on November 12, 2019 or following completion of the annual operating tests]
(exam security related item)
- 8. All simulator scenarios, approved for administration that will be administered in the 2019 annual exam, including which scenarios are assigned to a specific week and spreadsheets or outlines that show the usage of scenario events in all of the 2019 annual exams. [As available on November 12, 2019 or following completion of the annual operating tests] (exam security related item)
- 9. Self-assessment reports, condition reports, and/or Licensee Event Reports, written since the last biennial requalification inspection which document operator errors or performance problems that occurred in the actual plant/main control room, including the corrective actions. [November 12, 2019]
2 B.
On-site inspection material [December 2, 2019]:
- 1. Requalification training attendance records for the current two year biennial training cycle.
- 2. Examination results since last requalification inspection (weekly operating & written examinations); copies of examinations with pass/failure rates outside the average.
- 3. Two copies of simulator scenarios and JPMs (in-plant and simulator) that will be administered for this requalification exam during the week of December 2, 2019. (exam security related item)
- 4. All remedial training documentation for any licensed operator that failed an examination since the last requalification inspection.
- 5. List of all operators that reactivated their licenses since the last requalification inspection.
- 6. Records that support verification of time on shift under instruction and complete plant tours for both the reactivating operator and the supervising active license since the last requalification inspection, including:
- a. Documentation of time on shift under instruction.
- b. Security system and HP/dosimetry records for plant areas toured by reactivating individual and accompanying licensed operator.
- 7. Records providing documentation of maintenance of active license status (time on shift) for all licensed operators since last requalification inspection.
- 8. Medical records for all licensed (active and inactive) operators.
- 9. Simulator maintenance and testing records, including:
- a. List of all open simulator discrepancies
- b. List of all simulator discrepancies closed within the past 12 months
- c. List of simulator performance tests
- d. Simulator performance testing records and associated documentation