~ (i Houston
}
Lighting
& Power Company Electric Tower March 8, 1979 RQ Box 1700 ST-HL-AE-327 1
t l Houston.Teus 77001 SFN: 7-0100 Director, Region IV Office of Inspection S Enforcement Nuclear Regulatory Commission 611 Ryan Plaza Drive Arlington, Texas 76012
Dear Sir:
South Texas Project Units 1 S 2 Docket Nos. STN 50-498, STN 50-499 Interim Report on the Reportable Deficiency Concerninc Improper Anchor Bolt Material On February 8,1979, pursuant to 10 CFR 50.55(e), liouston Lighting S Power Company notified your office of a deficiency concerning the fabrication of anchor bolts from the improper material.
Attached is an interim report containing all available information.
A final report will be subnitted by June 1, 1979.
Very truly yours,
.4 E. A. Turner Vice President Power Plant Construction S Technical Services SSR/LRJ/bf Attachment cc: Messrs. D. G. Barker A. J. Granger C. Thrash (Baker S Botts)
R. Gordon Gooch (Baker S Botts)
J. R. Newman (Lowenstein, Newnan, Reis, Axelrad S Toll)
Wirector, Office of Inspection and Enforcement Nuclear Regulatory Commission Washington, D.C. 20555 k
\\
790319 0 \\b5 J
. - -