bI'IC DOCUMENT R UtlITED STATES OF AMERICA fiUCLEAR REGULATORY COMMISSION 10 1 o

.5 COMMISSIONERS:

s r~--o e

use:

g F E61 01979 '>@,

Joseph M. Hendrie, Chairman Victor Gilinsky N:

Richard T Kenr.edy

\\%

'+,.,,g f'

Peter A. Bradford A

' ' ' san John F. Ahearna b

U'A s

In the flatter of

)

)

VIhGIrllA ELECTRIC POWER COMPAtlY

)

Docket tios. 50-280 and (Surry Power Station, Units 1 & 2)

)

50-281

)

For Pselief Under 10 CFR 2.206

)

)

ORDER Pursuant to 10 CFR 2.772, the time for the Commission to review the February 1,1979 denial of enforcement action in connection with this facility is hereby extended until March 1, 1979.

It is so ORDERED.

For tbp Commission.

h.. b

,) O IILPI ~~

Se[c/ SAMUEL J. C retary of the, Commission i

Dated at Washington, D.C.,

this 15thlay of February,1979.