Review Schedule for License Renewal Application Has Been Prepared According to Agreement on Interface & Div of Responsibility Between NMSS & IE, W/Minor Adjustment. Lists Milestones in Review Schedule.Requests IE Input
ML19282A575
Person / Time
Site: 07000824
Issue date: 02/06/1979
From: Crow W
NRC OFFICE OF NUCLEAR MATERIAL SAFETY & SAFEGUARDS (NMSS)
To: Higginbotham L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
References
NUDOCS 7903050019
Download: ML19282A575 (2)


Text

e n

[

S UNITED STATES o

4 NUCLEAR REGULATORY COMMISSION g%,

j WASHINGTON, D. C. 20555 s

%...../

FEB 0 61979 ZO-S24_

SiiM-778 MEMORANDUli FOR:

L. B. Higginbotham, Assistant Director Division of Fuel Facilities and Material Safety Inspection FROM:

W. T. Crow, Section Leader Uraniun Fuel Fabrication Section Division of Fuel Cycle and Material Safety

SUBJECT:

LICENSE RENEWAL APPLICATION, BABC0CK & WILC0X LYNCHBURG RESEARCH CENTER, DOCKET 70-824 The license renewal application of the Babcock & Wilcox Lynchburg Research Center (LRC), (Docket 70-824, SNM-778) has been received and our review has begun. This renewal application is the first one received since the " Agreement on Interface and Division of Responsibility Between NMSS and I&E" has been accepted.

The review schedule has been prepared, along the lines of the agreement, with minor adjustments. We shall work with you in our review in accordance with the " Plan for Licensing Review and Inspections Related to Major Licensing Actions for Fuel Cycle Facilities" which is footnoted in the Interface Agreement. After completion of the review, we should like to diccuss possible changes to the Plan based on our experiences.

Major milestones in our review schedule include the following:

1.

Completion of initial safety reviews April 13,1979 2.

Completion of initial project manager review April 27,1979 3.

Site visit June 4, 1979 4.

Applicant response to NRC conments August 3, 1979 q90305006

s

\\

~%

e L. B. Higginbotham 5.

Completion of final safety reviews August 24, 1979 6.

Completion of final project manager review September 21, 1979

?.

Complete draft of integrated Safety Evaluation Report (SER)

October 12, 1979 8.

Prepare final SER November 2, 1979 9.

Issue renewal November 23, 1979 We should like your comments and recommendations on the renewal application, notification of your scheduled inspections of the LRC, and, in general to take the action required by the Plan to meet the above scheduled milestones.

As the review progresses, we shall be in contact with you to coordinate specific activities (e.g., request to accompany I&E members on inspections, discussions with licensee on application, meeting to discuss proposed license conditions).

d W. T. Crow, Section Leader Uranium Fuel Fabrication Section Division of Fuel Cycle and Material Safety

..