We "I~
PHILADELPHIA ELECTRIC COMPANY 9**
~3
~
Peach Bottosa Atotaic Power Station Delta,1%nnsylvania 1T314
.cw 6J a
October 19, 1979 Mr. Boyce H. Grier Office of Inspectiera and Enforcement Rugion 1 United States Nuclear Regulatory Coassission 631 Park Avenue King of Prussia, PA 19h06
SUBJECT:
REPORTABLE OCCURRENCE - PRO'@T NOTIFICATION Confi21 ming J. L Davenport's conversation with Mr. Greenman, Region 1, United. States Nuclear Regulatory Comunission on October 19, 1979 Referencer Docket No. 50-278 Peach Bottoss Unit 3 Technical Specification Referencess 6.9 2.a(9)
Report No. 3-79-29/1P occurrence Date:
cetober 19, 1979 Identification of Occurrence:
The piping systems inspection and measurement program being conducted t response to IE Bulletin 79.-14 has identified a damaged sway strut on the "C" Reactor Feed Pusep discharge line.
Sway strut 3-600-S2 was found to have a cracked rod end.
Apparent Cause_ vf Occurrencer Under investigation.
Analysis of Occurrence:
During routine 79-14 inspection procedures, a sway strut associated with the Unit 3 "C" Reactor Feed Pump discharge line was found to have a cracked rod end. Unit 3 reactor is in the cold shutdown condition for refueling and startup will not be initiated until the problem has been corrected.
Corrective Actiont+
A new sway strut has been ordered to replace 3-600-82, and is expected to arrive Tuesasy 10/23/79 Corrective action will be implemented prior to initiation of startup of Unit 3 reactor.
e b8 S
7912180
.g-
.. f oo o
J_ w o Ju o Ju S.
Previous Failures _
2-79-33/IP 2=79-37/IP 3-79-19/IP 3-79-23/IP 3-79-25/1P 3-79-26/IP 2'T9 Ish/1P 3-79-30/IP 3-79-31/IP 3-79-32/IP Very truly yours, M Nd I W. T. Ullrich StHLtion Superintendent WTU: cat