ML19276G913
| ML19276G913 | |
| Person / Time | |
|---|---|
| Site: | Phipps Bend |
| Issue date: | 08/13/1979 |
| From: | Mills L TENNESSEE VALLEY AUTHORITY |
| To: | James O'Reilly NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| Shared Package | |
| ML19276G914 | List: |
| References | |
| NCR-CEB-79-17, NUDOCS 7908280606 | |
| Download: ML19276G913 (1) | |
Text
.
9 553/79005 554/79003 TENNESSEE VALLEY AUTHORITY CH ATTANOOGA. TENNESSEE 37401 400 Chestnut Street Tower II August 13, 1979 Mr. James P. O'Reilly, Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Region II - Suite 3100 101 Marietta Street Atlanta, Georgia 30303
Dear Mr. O'Reilly:
PHIPPS BEND NUCLEAR PLANT - REPORTABLE DEFICIENCY - TENSILE ANCHOR CAPACITIES LOWER THAN ASSLTED IN DESIGN ALLOWASLES (NCR CEB Initial report of the subject deficiency was made to Mike Gouge, NRC-0IE, Region II on May 7, 1979. The first interim report was submitted on May 24, 1979. In compliance with paragraph 50.55(e) of 10 CFR Part 50, we are enclosing the second interim report of the subject deficiency. We anticipate transmitting the final report on or before December 21, 1979. If you have any questions concerning this matter, please call Tish Jenkins at FTS 854-2014.
Very truly yours, TENNESSEE VALLEY AUTHORITY L. M. Mills, Manager Nuclear Regulation and Safety Enclosure cc:
Mr. Victor Stello, Director (Enclosure)
Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, DC 20555 W's (
790gg 8 cccc,c,
(
204i 212 An Eaual Opportunity Employer