TIMELINE FOR ISSUANCE OF REGULATORY GUIDE FOR VOLCANIC HAZARDS AND ANTICIPATED STAKEHOLDER INVOLVEMENT Date Activity/Milestone Stakeholder Involvement?
October 10, 2019 Presentation to Advanced Reactors Stakeholders Meeting Yes October 21, 2019 Public meeting to discuss results of regulatory analysis and path forward for developing RG, and seek stakeholder input on content of the DG in development Yes November 8, 2019 Last day to submit comments on DG outline Yes Fall 2019/Winter 2020 Develop Draft Guide and route for internal review and concurrence No Winter 2020 ACRS briefings (tentative)
TBD March 10-12, 2020 RIC Poster Presentation Yes Spring 2020 Issue DG for public comment and temporary use by prospective applicants Yes Spring/Summer 2020 Public meeting to discuss DG, as issued, and receive stakeholder feedback and comments Yes Summer 2020 Public comment period closes, staff resolve public comments Yes Winter 2021 Receive feedback from prospective applicants using method in DG; update DG, if appropriate Yes Summer 2021 Incorporate lessons learned from acceptance and early safety review into DG No Winter 2022 Receive certified ANS 2.34 for endorsement No Spring 2022 Issue final RG, including ANS 2.34 endorsement, lessons learned from use by prospective applications, and resolutions of public comments on DG; likely public meeting to discuss key points of the final RG TBD ADAMS Package Accession Number: ML19276F199 ADAMS Accession Number: ML19276F244