October 3, 2019 Mr. Andrew Pullam Director - Nuclear Training Fermi Power Plant DTE Energy Company 6400 North Dixie Highway Newport, MI 48166

Dear Mr. Pullam:

On September 4, 2019, the U.S. Nuclear Regulatory Commission (NRC) administered the generic fundamentals examination (GFE) section of the written operator licensing examination to employees at your facility. Enclosed with this letter are copies of both forms of the examination, including answer keys, the grading results for your facility, and copies of the individual answer sheets for each of your employees. Please forward the results to the individuals along with the copies of their respective answer sheets. A P in the RESULTS column indicates that the individual achieved a passing grade of 80 percent or better on the GFE, while an F indicates that the individual failed the exam.

If you have any questions concerning this examination, please contact Mr. Eric Cushing at 301-415-1064.

Sincerely, Robert J. Digitally signed by Robert J. Orlikowski Orlikowski Date: 2019.10.03 07:56:31

-05'00' Robert J. Orlikowski, Chief Operations Branch Division of Reactor Safety Docket No. 50-341 Enclosures (Non-Public):

1. Examination Forms A and B with answers
2. Examination Results Summary for Fermi Power Plant
3. Individual Answer Sheets

A. Pullam 2 DOCUMENT NAME:

Fermi GFE results Sept 2019.docx TEMPLATE#: NRR -079 OFFICE RIII/DRS/OB:OLA RIII/DRS/OB:BC NAME CSchmidt CS ROrlikowski RJO DATE 10/02/19 10/ 3 /19 OFFICIAL RECORD COPY