MINUTES: MANAGEMENT REVIEW BOARD MEETING OF FLORDIA SEPTEMBER 17, 2019 The meeting attendees were as follows:
Management Review Board Steve West, OEDO Jack Giessner, Region III Robert Lewis, NMSS Sherrie Flaherty. OAS Representative Mary Spencer, OGC, IMPEP Team Lizette Roldan-Otero, NMSS/MSST Jennifer Dalzell, Region III Celimar Valentin-Rodriguez, NMSS/MSST Brian Goretzki, State of Arizona Penny Lanzisera, Region I Beth Schilke, Commonwealth of Virginia John Miller, Region I RSAO State of Florida Cynthia Becker Jorge Laguna Kevin Kunder Mike Stephens Joy Stephenson Staff Kevin Williams, NMSS/MSST Stephen Poy, NMSS/MSST Paul Michalak, NMSS/MSST Joe OHara, NMSS/MSST Robert Johnson, NMSS/MSST John Thorp, NRC/OIG Duncan White, NMSS/MSST Janelle Wiggs, NRC/OIG Jazel Parks, NMSS/MSST Members of the Public David Turberville, State of Alabama Phil Peterson, State of Colorado Topics discussed during the meeting included:
- 1. Convention. Mr. Robert Johnson convened the meeting at approximately 1:00 p.m.
(ET). He noted that this Management Review Board (MRB) meeting was open to the public. Introductions of the attendees were conducted.
- 2. Florida IMPEP Review. Dr, Lizette Roldan-Otero, Team Leader, led the presentation of the Florida Integrated Materials Performance Evaluation Program (IMPEP) review results to the MRB. She summarized the review and the teams findings for the indicators reviewed. The on-site review was conducted by a team composed of technical staff members from the U.S. Nuclear Regulatory Commission (NRC), the State of Arizona, and the Commonwealth of Virginia during the period of June 24-28, 2019. A draft report was issued to Florida for factual comment on July 31, 2019. Dr. Roldan-Otero reported that the team found Floridas performance was satisfactory for five out of the seven indicators reviewed; satisfactory, but needs improvement for Technical Quality of Licensing; and unsatisfactory for Compatibility Requirements.
Florida MRB Meeting Minutes Page 2
- 3. Performance Indicators.
a) Mr. John Miller reviewed and presented the common performance indicator, Technical Staffing and Training. His presentation corresponded to Section 3.1 of the proposed final IMPEP report. The MRB, the team, and Florida representatives briefly discussed the status of the staff hired during the review period and the impact of vacancies on the Agreement State Program.
The team found Floridas performance with respect to this indicator to be satisfactory and the MRB agreed.
b) Mr. John Miller reviewed and presented the common performance indicator, Status of Materials Inspection Program. His presentation corresponded to Section 3.2 of the proposed final IMPEP report. The MRB, the team, and Florida representatives briefly discussed inspection findings.
The team found Floridas performance with respect to this indicator to be satisfactory and the MRB agreed.
c) Ms. Penny Lanzisera reviewed and presented the common performance indicator, Technical Quality of Inspections. Her presentation corresponded to Section 3.3 of the proposed final IMPEP report. The MRB, the team, and Florida representatives discussed the deficiencies identified during the performance of the inspection accompaniments with regards to health, safety, and security, as well as the actions the program had taken to address them. In addition, the MRB, the team, and Florida discussed the recommendation made by the team.
The team found Floridas performance with respect to this indicator to be satisfactory, but need improvement and the MRB agreed. The MRB also agreed with the teams recommendation.
d) Ms. Jennifer Dalzell and Beth Schilke reviewed the common performance indicator, Technical Quality of Licensing Actions. Ms. Dalzell presented the teams findings. Her presentation corresponded to Section 3.4 of the proposed final IMPEP report. The MRB, the team, and Floridas representatives discussed the teams findings, as well as the actions the program had taken to address them. In addition, the MRB, the team, and Florida discussed the recommendation made by the team.
The team found Floridas performance with respect to this indicator to be satisfactory and the MRB agreed. The MRB also agreed with the teams recommendation.
e) Mr. Brian Goretzki reviewed and presented the common performance indicator, Technical Quality of Incident and Allegation Activities. His presentation corresponded to Section 3.5 of the proposed final IMPEP report. The MRB, the team, and Florida representatives discussed incidents of high risk and protecting allegers identities.
The team found Floridas performance with respect to this indicator to be satisfactory and the MRB agreed.
Florida MRB Meeting Minutes Page 3 f) Dr. Roldan-Otero reviewed and presented the non-common performance indicator, Compatibility Requirements. Her presentation corresponded to Section 4.1 of the proposed final IMPEP report. The MRB, the team, and Florida representatives discussed the States overdue regulations, and program elements, as well as the actions the program has taken to address them. In addition, the MRB, the team, and Florida discussed the recommendation made by the team.
The team found Floridas performance with respect to this indicator to be unsatisfactory and the MRB agreed. The MRB also agreed with the teams recommendation.
g) Dr. Celimar Valentin-Rodriguez reviewed the non-common performance indicator, Sealed Source and Device Evaluation Program. Her presentation corresponded to Section 4.2 of the proposed final IMPEP report. The MRB, the team, and Florida representatives discussed the training and qualification of staff, including the updating of the training qualification journal.
The team found Floridas performance with respect to this indicator to be satisfactory and the MRB agreed.
- 4. MRB Consultation/Comments on Issuance of Report. The team recommended, and the MRB agreed, that the Florida Agreement State Program be found adequate to protect public health and safety, but needs improvement and not compatible with the NRC's program. The team recommended that the next IMPEP review take place in approximately 4 years with a periodic meeting in approximately 2 years. In addition, the team recommended that Florida enter a period of Monitoring. The MRB agreed with the team that the next IMPEP take place in 4 years. However, the MRB determined that a period of Monitoring was not warranted at this time, and instead decided that two periodic meetings should be held in approximately 1 year, and 3 years, respectively.
The final report may be found in the ADAMS using the Accession Number ML19262D631.
- 5. Precedents/Lessons Learned. None
- 6. Comments from Members of the Public. None
- 7. Adjournment. The meeting was adjourned at approximately 2:55 p.m. (ET)