Combustion Engineering Inc.
Docket No. 99900036/79-01 NOTICE OF DEVIATION Based on the results of an NRC inspection conducted on February 26 -
March 2,1979, it appeared that certain of your activities were not conducted in full compliance with NRC requirements as indicated below:
Criterion V of Appendix B to 10 CFR 50 states in part that " Activities affecting quality shall be prescribed by documented instructions, proce-dures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings...."
In addition, weld specification GTA 1.1.-100-0 requires welding to be accomplished between 90 to 110 amps.
Contrary to the above requirements, it was observed that welding to specification GTA 1.1.-100-0 on an "eggerate assembly" identified by heat No. NX 8362-D and contract No. 72273 was being accomplished with 136 amps.