ML19270G541

From kanterella
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in IE Insp Rept 50-482/79-03.Corrective Actions:Intensive Training Program Conducted for Concrete Crews & Concrete Control Procedures Revised
ML19270G541
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 04/23/1979
From: Koester G
KANSAS GAS & ELECTRIC CO.
To: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML19270G539 List:
References
NUDOCS 7906130033
Download: ML19270G541 (2)


Text

-

1 i

' l KANSAS GAS AND ELECTRIC COAfPANY

' TPes mLsc7seeC COMm4NF GLENN L. MQE S T E M vict Patteot=v opt mations April 23, 1979 Mr. W.C. Seidle, Chief Reactor Construction and Engineering Support Branch U.S. Nuclear Regulatory Commission Region IV 611 Ryr.n Plaza Drive, Suite 1000 Arlington, Texas 76011

Subject:

Response to Inspection Report 50-482/79-03

Dear Mr. Seidle:

This letter is written in response to your letter of March 14, 1979,

<nich transmitted Inspection Report 50-482/79-03. As requested, each finding is being addressed in three parts:

a)

Corrective steps which have been taken and the results

achieved, b)

Corrective steps which will be taken to avoid further non-compliance, and c)

The dates when full compliance will be achieved.

Finding During placement OC-241-W-2 on November 14, 1978, the constructor caused concrete to flow underneath the containment building equip-ment hatch. Due to the equipment hatch diameter of twenty feet, the concrete was caused to flow a distance greater than five feet from the point of deposition.

2?.37 114

Response

a)

A Work Hold Agreement was issued on December 18, 1978, to stop the placement of all safety-related concrete. An Ad Hoc Committee was established by Daniel to investigate quality-related problems and to make recommendations for their solution.

7906130033 201 N. Market - Wichita, Kansas --- Mail Address: P. O. Box 208 / Wichita, Kansas 672cl - Telephone: Area Code (316) 264-1111

Mr. W.C. Seidle April 23, 1979 The charter of this Committee was established by Mr. Howard McCall's letter of December 16, 1978. The charter is also described in Mr. Seyfrit's letter to me dated December 19, 1978. The Committee performed their investigations and issued a report containing specific recommendations for improving the quality of work. These recommendations were carried out and were verified. The Work Hold was lifted on March 3, 1979.

However, when concreting work resumed, a similar type incident occurred on March 8,1979, during a placement which was identified as being difficult. A KG&E Stop Work Order for all "Q" concrete was issued, and Daniel issued their own Stop Work Order on difficult concrete placements. Additional corrective action was taken, including replacing two supervisors responsible for concrete work and re-training of the concrete crew.

On March 22, release of our Stop Work Order was made, while Daniel's hold on difficult placements remained in effect.

After several nondifficult placements were completed satis-factorily, Daniel lifted their Hold and proceeded to make difficult placements. Daniel is making only one difficult placement at a time and will proceed without restriction after high confidence levels are established.

Since March 22, no placing errors have been identified.

b)

Intensive training programs have been conducted for all concrete cre,ws and for supervisory personnel responsible for concrete activities. Procedures for controlling concrete activities have been revised to imprcve their effectiveness.

c)

All corrective actions are completed and full compliance achieved.

Yours very truly, ft/h Y

GLK:bb 2337 115