ML19270F225
| ML19270F225 | |
| Person / Time | |
|---|---|
| Site: | Millstone |
| Issue date: | 01/29/1979 |
| From: | Counsil W NORTHEAST UTILITIES |
| To: | Grier B NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| References | |
| AEC-MP3-178, NUDOCS 7902050101 | |
| Download: ML19270F225 (2) | |
Text
.
NORTHEAST NORTHEAST UTILITIES SERVICE COMPANY LJTiblTIES iia iT D CONNECTICUT 06101 203-666-6911 January 29, 1979 United States Nuclear Regulatory Commission ATTN: Mr. B. H. Grier, Director Office of Inspection and Enforcement Region I 631 Park Avenue King of Prussia, Pennsylvania 19406 Gentlemen:
Docket No. 50-423 AEC-MP3-178
SUBJECT:
Millstone Unit No. 3 WGC-79-3-21 Reporting of Deficiencies In Design & Construction
References:
1.
D.C. Switzer letter to Dr. D.C. Knuth, dated February 18, 1976 (AEC-MP3-109).
2.
D.C. Switzer letter to J.P. O'Reilly, dated September 8,1976 ( AEC-MP3-ll7).
3.
D.C. Switzer letter to J.P. O'Reilly, dated April 19,1977 (AEC-MP3-140).
4.
D.C. Switzer letter to B.H. Grier, dated November 15,1977 ( AEC-MP3-158).
5.
D.C. Switzer letter to B.H. Grier, dated March 9,1978 (AEC-MP3-167).
6.
W.G. Counsil letter to B.H. Grier, dated June 15, 1978 ( AEC-MP3-171 ).
Please refer to our letter dated June 15,1978, AEC-MP3-171, in which we stated that we had inspected 50 Category I pipe spools of TUBECO and would report again when our inspection effort on 100 spools was complete.
The inspection of 100 QA Category I pipe spools of TUBEC0 has now been completed.
The results of this inspection indicate that TUBECO has properly implemented its QA Category I program.
During this period, however, TUBECO itself, identified to our agent an _currence of improper material usage. As a result of this, and in order to provide additional assurance of code compliance, the inspection hold point oa the pipe cutting operation is being retained on ASME III work.
In addition, documentation for ASME III piping and spools is being reviewed prior to releasing hardware for shipment in accordance with our agent's standard program.
b QO
"/ 9 0 2 l)g o g og y9 1 E Co~~ECT,Cu, uo 1 A~
rcrR CooPA~Y THE HARTFORD EL ECTRIC UGkT CCUFANY WESTERN MASSACHUSETTS ELECTRIC COMPANY
\\
HOLYOkE W ATER POWER CCMPANY NORTHE AST UTILITIES SFRvlCE COMPANY We believe these measures, in conjunction with continued periodic audits of TUBEC0's QA program, provide adequate assurance of TUBEC0's quality performance; and we consider the above-referenced Deficiency Report satisfactorily resolved.
Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY
/
W(
W. G. Counsil Vice President Nuclear Engineering & Operations cc: United States Nuclear Regulatory Comission Office of Inspection and Enforcement Washington, D.C.
20555