Startup Test 9 for Period 780822 Through 781122.Since NRC Has Not Authorized Operation at Power Levels in Excess of 70%,no Further Power Tests Were Performed During Period
ML19269D159
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 02/20/1979
From:
PUBLIC SERVICE CO. OF COLORADO
To:
References
P-79047, NUDOCS 7902270402
Download: ML19269D159 (2)


Text

'

s

\

nlE FORT ST. VRAIN

'\

t.

INITIAL APPROACH TO 'g

\

POWER IESTS (B-SERIES)

.\

\

\

INTERIM REPORT 9 Report for Period Ending Nove=ber 22, 1978 79022704ot

' - Interim Report 8 covering the 90 day period ending August 22, 1978, reported the completion of all tests up to 70% of plant load. Since the Nuclear Regula tory Commission did no t release the plant for operation at power levels in excess of 70%, no further Initial Approach to Power Tests were performed during the 90 days ending November 22, 1979.

Future interim reports will report the results of any s tartup tests.