8 APPENDIX A NOTICE OF VIOLATION Boston Edison Company Docket No. 50-293 Based on the results of an NRC inspection conducted on October 22-24, 30, 31 - November 1-3, 1978, it appears that certain of your activities were conducted in full compliance with the Code of Federal Regulations and your Facility License DPR-35 as indicated below.
This is an infraction.
Technical Specification 6.8.A states in part: " Written procedures...
shall be established, implemented..."
Procedure 8.A.9, Revision 0 dated October 24, 1978, " Weekly Turbine Tests," states in part A.9.A, "... turbine control valves will not be tested when unit load is greater than 70%..."
Contrary to the above, procedure 8.A.9 was not lollowed on Octo-ber 30, 1978 in that turbine control valves were tested at 70%, at 75%, and an attempt was made to test the valves at 80% unit load without utilization of the prescribed methods for effecting changes to procedures.