Notice of Violation for Insp on 781022-24,30,31 & 1101-03
ML19269B984
Person / Time
Site: Pilgrim
Issue date: 11/22/1978
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML19269B979 List:
References
50-293-78-25, NUDOCS 7901190180
Download: ML19269B984 (1)


Text

.

8 APPENDIX A NOTICE OF VIOLATION Boston Edison Company Docket No. 50-293 Based on the results of an NRC inspection conducted on October 22-24, 30, 31 - November 1-3, 1978, it appears that certain of your activities were conducted in full compliance with the Code of Federal Regulations and your Facility License DPR-35 as indicated below.

This is an infraction.

Technical Specification 6.8.A states in part: " Written procedures...

shall be established, implemented..."

Procedure 8.A.9, Revision 0 dated October 24, 1978, " Weekly Turbine Tests," states in part A.9.A, "... turbine control valves will not be tested when unit load is greater than 70%..."

Contrary to the above, procedure 8.A.9 was not lollowed on Octo-ber 30, 1978 in that turbine control valves were tested at 70%, at 75%, and an attempt was made to test the valves at 80% unit load without utilization of the prescribed methods for effecting changes to procedures.