Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217H4661999-10-18018 October 1999 Forwards Changes to EPIPs IAW 10CFR50.54(q) & 10CFR50,App E, Section V.Details of Changes Encl ML20217H6341999-10-15015 October 1999 Requests Renewal of Operator Licenses for Listed Personnel. Current Licenses for Kh Curran,Lm Gerlach,Rc Weber & Bt Rhodes Will Expire in Nov 1999.Proprietary NRC Form 398 & NRC Form 396 Encl.Proprietary Info Withheld ML20217H6251999-10-15015 October 1999 Requests Renewal of Operator Licenses for Listed Personnel. Current Licenses for MR Kahn,Aj Mclaughlin,De Montgomery & Kr Murphy Will Expire in Nov 1999.Proprietary NRC Form 398 & NRC from 396 Encl.Proprietary Info Withheld ML20217F4301999-10-14014 October 1999 Responds to 991012 Rai,Based on 991001 Telcon Re Suppl to Request for TS Change to Revise MCPR Safety Limit & Add Approved Siemens Topical Rept for LaSalle County Station, Unit 1 ML20217D3191999-10-12012 October 1999 Submits Request for Addl Info Re Licensee 990707 Proposed License Amend to Revise Min Critical Power Ratio.Listed Questions Were Discussed with Util in 991001 Telcon ML20217C1671999-10-0808 October 1999 Provides Suppl to RAI for Approval of Unreviewed Safety Question Re Assessment of Certain safety-related Concrete Block Walls at LaSalle County Station,Units 1 & 2 ML20217A7601999-10-0606 October 1999 Forwards Insp Repts 50-373/99-15 & 50-374/99-15 on 990729-0916.One Violation of NRC Requirements Occurred & Being Treated as Ncv,Consistent with App C of Enforcement Policy ML20212M0931999-10-0404 October 1999 Refers to 990922-23 Meeting Conducted by Region II at LaSalle Nuclear Power Station.Purpose of Visit,To Meet with Licensee Risk Mgt Staff to Discuss Util Initiatives in Risk Area & to Establish Dialog Between SRAs & Risk Mgt Staff 05000373/LER-1999-003, Forwards LER 99-003-00 IAW 10CFR50.73(a)(2)(iv).Commitments for Submittal Also Encl1999-10-0404 October 1999 Forwards LER 99-003-00 IAW 10CFR50.73(a)(2)(iv).Commitments for Submittal Also Encl ML20216J8241999-09-30030 September 1999 Notifies of Removal of NRC Headquarters & Region III Offices from Controlled Copy Distribution of Certain CE Documents. Specific Documents,Associated Controlled Copy Numbers & NRC Location Affected Are Shown on Attachment to Ltr ML20217A6201999-09-30030 September 1999 Advises of NRC Plans for Future Insp Activities at Facility for Licensee to Have Opportunity to Prepare for Insps & to Provide NRC Feedback on Any Planned Insps Which May Conflict with Plant Activities.Plant Issue Matrix & Insp Plan Encl ML20212E7171999-09-22022 September 1999 Forwards RAI Re Requesting Approval of License Amend to Use Different Methodology & Acceptance Criteria for Reassessment of Certain Masonry Walls Subjected to Transient HELB Pressurization Loads 05000374/LER-1999-002, Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(iv).Commitments Made by Util Are Encl1999-09-20020 September 1999 Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(iv).Commitments Made by Util Are Encl ML20212C0591999-09-17017 September 1999 Informs That NRC Reviewed Licensee Justifications for Deviations from NEDO-31558 & Determined That Justifications acceptable.Post-accident Neutron Flux Monitoring Instrumentation Acceptable Alternative to Reg Guide 1.97 ML20212A3581999-09-13013 September 1999 Confirms That Fuel MCPR Data for LaSalle County Station,Unit 1,Cyle 9,sent by Ltr Meets Condition 2,as Stated in 970509 NRC Ltr ML20211Q9911999-09-10010 September 1999 Informs That License SOP-4048-4,for Wp Sly May Be Terminated Due to Individual Retiring ML20212A1141999-09-10010 September 1999 Forwards RAI Re Licensee 990519 Amend Request,Which Proposed to Relocate Chemistry TSs from TS to licensee-controlled Documents.Response Requested by 990930,so That Amend May Be Issued to Support Upcoming Unit 1 Refueling Outage ML20211P2211999-09-0808 September 1999 Forwards Insp Repts 50-373/99-14 & 50-374/99-14 on 990809- 13.No Violations Noted.Insp Concluded That Emergency Preparedness Program Maintained in Good State of Operational Readiness ML20212A8571999-09-0707 September 1999 Informs That Proprietary Document, Power Uprate SAR for LaSalle County Station,Units 1 & 2, Rev 2,Class III, NEDC-32701P,submitted in ,Marked Proprietary,Will Be Withheld from Public Disclosure,Per 10CFR2.790(b)(5) ML20211Q6861999-09-0606 September 1999 Informs That NRC Tentatively Scheduled Initial Licensing Exam for Plant License Applicants During Wks of 001113 & 20. Validation of Exam Will Occur at Station During Wk of 001023 05000374/LER-1999-001, Forwards LER 99-001-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Encl1999-09-0303 September 1999 Forwards LER 99-001-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Encl ML20211M1151999-08-31031 August 1999 Requests That Following Eleven Individuals Take BWR Gfes of Written Operator Licensing Exam to Be Administered on 991006 ML20211G1831999-08-27027 August 1999 Provides Addl Clarification of Proposed Refueling Practices Under Proposed Core Alterations Definition Re 990813 Application for Amend to TS ML20211G1221999-08-27027 August 1999 Forwards fitness-for-duty Program Performance Data for Each of Comm Ed Nuclear Power Stations & Corporate Support Employees within Scope of Rule for six-month Period Ending 990630,IAW 10CFR26.71(d) ML20211F8731999-08-25025 August 1999 Forwards Insp Repts 50-373/99-13 & 50-374/99-13 on 990804-06 & 09-11.No Violations Noted.Fire Protection Program Strengths Includes Low Number of Fire Protection Impairments & Excellent Control of Transient Combustibles ML20210U3201999-08-17017 August 1999 Forwards Insp Repts 50-373/99-12 & 50-374/99-12 on 990623-0728.No Violations Noted ML20210N5651999-08-0606 August 1999 Forwards Rev 8 to Nuclear Generating Stations Emergency Plan, for Plants.With Summary of Changes ML20210M9131999-08-0202 August 1999 Forwards Response to NRC AL 99-02, Operating Reactor Licensing Action Estimates, for Fys 2000 & 2001 for Comed 05000373/LER-1999-002, Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Listed1999-07-23023 July 1999 Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Listed ML20210E0501999-07-22022 July 1999 Submits Summary of 990630 Management Meeting Re Licensee Performance Activities Since Start Up of Unit 2.List of Attendees & Matl Used in Presentation Enclosed ML20210B7071999-07-16016 July 1999 Responds to Requesting Review & Approval of Three Proposed Changes to Ceco QA TR,CE-1A Per 10CFR50.54(a)(3) & 10CFR50.4(b)(7) ML20209H5171999-07-15015 July 1999 Discusses 990701 Telcon Re Arrangements for NRC to Inspect Licensed Operator Requalification Program at LaSalle County Nuclear Generating Station for Weeks of 990913,1018 & 1129 ML20209G4031999-07-14014 July 1999 Forwards Insp Repts 50-373/99-11 & 50-374/99-11 on 990614-18.No Violations Noted ML20209E1211999-07-14014 July 1999 Submits mid-cycle Rev of COLR IAW LaSalle County Tech Spec 6.6.A.6.d.Rev to COLR Was Necessary Due to Implementation of TS Change Approved by Ltr Dtd 990212,which Changed Turbine Stop Valve & Turbine Control Valve Scram ML20209F6931999-07-13013 July 1999 Forwards Insp Repts 50-373/99-04 & 50-374/99-04 on 990513-0622.No Violations Noted.Determined That Multiple Challenges to Main Control Room Operators Occurred During Insp Period Due to Human Performance Weaknesses ML20210C1521999-07-0909 July 1999 Forwards Post-Outage (90 Day) Summary Rept for ISI Examinations & Repair/Replacement Activities Conducted from Beginning of First Insp Period of Second ten-yr Insp Interval Through L2R07 Refueling Outage ML20209G3901999-07-0909 July 1999 Informs NRC of Status of Commitments & Requests NRC Concurrence for Use of ASME Section III App F Acceptance Criteria to Permanently Qualify Units 1 & 2 Penetrations M-49 & M-50 ML20209E0341999-07-0909 July 1999 Provides NRC with Siemens Power Corp (SPC) Fuel & GE Fuel MCPR Data for LaSalle Unit 1 Cycle 9.LaSalle Unit 1 Is Currently Scheduled to Start Cycle 9 in 991101 ML20209E0361999-07-0808 July 1999 Forwards LaSalle County Station Unit 2 Cycle 8 Startup Test Rept Summary,Iaw TS NPF-18,Section 6.6.A.1.Startup Test Program Was Satisfactorily Completed on 990501 ML20196J9131999-07-0101 July 1999 Submits Status of Nuclear Property Insurance Currently Maintained for Braidwood,Byron,Dresden,Lasalle County,Quad Cities & Zion Nuclear Power Stations,Per 10CFR50.54(w)(3) ML20196J9061999-07-0101 July 1999 Provides Evidence That Util Maintains Guarantee of Payment of Deferred Premiums in Amount of $10 Million for Each of Thirteen Reactors,Per 10CFR140.21 ML20209B8241999-06-30030 June 1999 Forwards Five 3.5 Inch Computer Diskettes Containing Revised Annual Dose Repts for 1994 Through 1998 for Individuals Receiving Neutron Dose Not Previously Included in Reported Total Effective Dose Equivalent Values.Without Diskettes ML20196J4711999-06-30030 June 1999 Discusses Closure of GL 92-01,Rev 1,Suppl 1, Rv Structural Integrity, Issued on 950519 to Plant,Units 1 & 2 ML20212J0311999-06-21021 June 1999 Informs of Actions Taken to Close Remaining Open Items in .Attachment Provides Detailed Justification for Closure of Open Items in Sections 5.2.2 & 5.2.8 ML20196B1951999-06-18018 June 1999 Informs NRC That Do Werts,License OP-30373-2,no Longer Requires Use of NRC License for LaSalle County Station. License May Be Terminated ML20195J7761999-06-15015 June 1999 Submits Request Relief CR-23,requesting Relief from Code Required Selection & Examinations of Noted Integral Attachments & Proposes to Utilize Alternative Selection & Examination Requirements Similar to Code Case N-509 ML20196G8021999-06-15015 June 1999 Requests Renewal of SRO License for Vv Masterson.Current License for Vv Masterson Will Expire Jul 1999.NRC Forms 398 & 396,encl.Without Encls ML20195G7101999-06-11011 June 1999 Informs That Effective 990514,GH Mccallum,License SOP-31412, No Longer Requires Use of NRC License for LaSalle Station. License Should Be Terminated ML20195D6351999-06-0404 June 1999 Notifies NRC of Actions That Has Been Taken in Accordance with 10CFR26, Fitness for Duty Programs ML20207D2821999-05-27027 May 1999 Requests That Implementation Date for Unit 1 Be Changed Prior to Startup for L1C10 to Allow Best Allocation of Resources to Implement Unit 1 Amend Prior to Startup for Either L1C9 or L1C10.Unit 2 Will Implement Mod IAW Request 1999-09-08
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML20217H4661999-10-18018 October 1999 Forwards Changes to EPIPs IAW 10CFR50.54(q) & 10CFR50,App E, Section V.Details of Changes Encl ML20217H6251999-10-15015 October 1999 Requests Renewal of Operator Licenses for Listed Personnel. Current Licenses for MR Kahn,Aj Mclaughlin,De Montgomery & Kr Murphy Will Expire in Nov 1999.Proprietary NRC Form 398 & NRC from 396 Encl.Proprietary Info Withheld ML20217H6341999-10-15015 October 1999 Requests Renewal of Operator Licenses for Listed Personnel. Current Licenses for Kh Curran,Lm Gerlach,Rc Weber & Bt Rhodes Will Expire in Nov 1999.Proprietary NRC Form 398 & NRC Form 396 Encl.Proprietary Info Withheld ML20217F4301999-10-14014 October 1999 Responds to 991012 Rai,Based on 991001 Telcon Re Suppl to Request for TS Change to Revise MCPR Safety Limit & Add Approved Siemens Topical Rept for LaSalle County Station, Unit 1 ML20217C1671999-10-0808 October 1999 Provides Suppl to RAI for Approval of Unreviewed Safety Question Re Assessment of Certain safety-related Concrete Block Walls at LaSalle County Station,Units 1 & 2 05000373/LER-1999-003, Forwards LER 99-003-00 IAW 10CFR50.73(a)(2)(iv).Commitments for Submittal Also Encl1999-10-0404 October 1999 Forwards LER 99-003-00 IAW 10CFR50.73(a)(2)(iv).Commitments for Submittal Also Encl ML20216J8241999-09-30030 September 1999 Notifies of Removal of NRC Headquarters & Region III Offices from Controlled Copy Distribution of Certain CE Documents. Specific Documents,Associated Controlled Copy Numbers & NRC Location Affected Are Shown on Attachment to Ltr 05000374/LER-1999-002, Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(iv).Commitments Made by Util Are Encl1999-09-20020 September 1999 Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(iv).Commitments Made by Util Are Encl ML20211Q9911999-09-10010 September 1999 Informs That License SOP-4048-4,for Wp Sly May Be Terminated Due to Individual Retiring 05000374/LER-1999-001, Forwards LER 99-001-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Encl1999-09-0303 September 1999 Forwards LER 99-001-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Encl ML20211M1151999-08-31031 August 1999 Requests That Following Eleven Individuals Take BWR Gfes of Written Operator Licensing Exam to Be Administered on 991006 ML20211G1831999-08-27027 August 1999 Provides Addl Clarification of Proposed Refueling Practices Under Proposed Core Alterations Definition Re 990813 Application for Amend to TS ML20211G1221999-08-27027 August 1999 Forwards fitness-for-duty Program Performance Data for Each of Comm Ed Nuclear Power Stations & Corporate Support Employees within Scope of Rule for six-month Period Ending 990630,IAW 10CFR26.71(d) ML20210N5651999-08-0606 August 1999 Forwards Rev 8 to Nuclear Generating Stations Emergency Plan, for Plants.With Summary of Changes ML20210M9131999-08-0202 August 1999 Forwards Response to NRC AL 99-02, Operating Reactor Licensing Action Estimates, for Fys 2000 & 2001 for Comed 05000373/LER-1999-002, Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Listed1999-07-23023 July 1999 Forwards LER 99-002-00,IAW 10CFR50.73(a)(2)(i).Commitments Made by Util Are Listed ML20209E1211999-07-14014 July 1999 Submits mid-cycle Rev of COLR IAW LaSalle County Tech Spec 6.6.A.6.d.Rev to COLR Was Necessary Due to Implementation of TS Change Approved by Ltr Dtd 990212,which Changed Turbine Stop Valve & Turbine Control Valve Scram ML20210C1521999-07-0909 July 1999 Forwards Post-Outage (90 Day) Summary Rept for ISI Examinations & Repair/Replacement Activities Conducted from Beginning of First Insp Period of Second ten-yr Insp Interval Through L2R07 Refueling Outage ML20209E0341999-07-0909 July 1999 Provides NRC with Siemens Power Corp (SPC) Fuel & GE Fuel MCPR Data for LaSalle Unit 1 Cycle 9.LaSalle Unit 1 Is Currently Scheduled to Start Cycle 9 in 991101 ML20209G3901999-07-0909 July 1999 Informs NRC of Status of Commitments & Requests NRC Concurrence for Use of ASME Section III App F Acceptance Criteria to Permanently Qualify Units 1 & 2 Penetrations M-49 & M-50 ML20209E0361999-07-0808 July 1999 Forwards LaSalle County Station Unit 2 Cycle 8 Startup Test Rept Summary,Iaw TS NPF-18,Section 6.6.A.1.Startup Test Program Was Satisfactorily Completed on 990501 ML20196J9131999-07-0101 July 1999 Submits Status of Nuclear Property Insurance Currently Maintained for Braidwood,Byron,Dresden,Lasalle County,Quad Cities & Zion Nuclear Power Stations,Per 10CFR50.54(w)(3) ML20196J9061999-07-0101 July 1999 Provides Evidence That Util Maintains Guarantee of Payment of Deferred Premiums in Amount of $10 Million for Each of Thirteen Reactors,Per 10CFR140.21 ML20209B8241999-06-30030 June 1999 Forwards Five 3.5 Inch Computer Diskettes Containing Revised Annual Dose Repts for 1994 Through 1998 for Individuals Receiving Neutron Dose Not Previously Included in Reported Total Effective Dose Equivalent Values.Without Diskettes ML20212J0311999-06-21021 June 1999 Informs of Actions Taken to Close Remaining Open Items in .Attachment Provides Detailed Justification for Closure of Open Items in Sections 5.2.2 & 5.2.8 ML20196B1951999-06-18018 June 1999 Informs NRC That Do Werts,License OP-30373-2,no Longer Requires Use of NRC License for LaSalle County Station. License May Be Terminated ML20196G8021999-06-15015 June 1999 Requests Renewal of SRO License for Vv Masterson.Current License for Vv Masterson Will Expire Jul 1999.NRC Forms 398 & 396,encl.Without Encls ML20195J7761999-06-15015 June 1999 Submits Request Relief CR-23,requesting Relief from Code Required Selection & Examinations of Noted Integral Attachments & Proposes to Utilize Alternative Selection & Examination Requirements Similar to Code Case N-509 ML20195G7101999-06-11011 June 1999 Informs That Effective 990514,GH Mccallum,License SOP-31412, No Longer Requires Use of NRC License for LaSalle Station. License Should Be Terminated ML20195D6351999-06-0404 June 1999 Notifies NRC of Actions That Has Been Taken in Accordance with 10CFR26, Fitness for Duty Programs ML20207D2821999-05-27027 May 1999 Requests That Implementation Date for Unit 1 Be Changed Prior to Startup for L1C10 to Allow Best Allocation of Resources to Implement Unit 1 Amend Prior to Startup for Either L1C9 or L1C10.Unit 2 Will Implement Mod IAW Request ML20195B2301999-05-19019 May 1999 Requests Approval of Proposed Changes to QA Topical Rept CE-1-A,rev 66a.Attachment a Describes Changes,Reason for Change & Basis for Concluding That Revised QAP Incorporating Proposed Changes Continues to Satisfy 10CFR50AppB ML20206R4561999-05-12012 May 1999 Provides Notification That Ws Jakielski,License SOP-30168-3, Is Being Reassigned & No Longer Requires Use of NRC License, IAW 10CFR50.74 05000373/LER-1999-001, Forwards LER 99-001-00,IAW 10CFR50.73(a)(2)(ii).Attachment a Provides Commitments for Submittal1999-05-0707 May 1999 Forwards LER 99-001-00,IAW 10CFR50.73(a)(2)(ii).Attachment a Provides Commitments for Submittal ML20206K7081999-05-0707 May 1999 Forwards 10CFR50.46(a)(3) Rept Re Significant Change in Calculated Pct.Loca Analyses for Both GE Fuel & Siemens Power Corp Fuel Demonstrates Results within All of Acceptance Criteria Set Forth in 10CFR50.46 ML20206K1861999-04-30030 April 1999 Informs That in Comed Submitted Annual Exposure Rept for Personnel Receiving Greater than 0 Mrem/Yr Rather than 100 Mrem/Yr.Updated Rept Limiting Data to Personnel Receiving Greater than 100 Mrem/Yr,Attached ML20206R0751999-04-30030 April 1999 Forwards License Renewal Applications & Certification of Medical Examinations for LaSalle County Station Personnel Whose Licenses Expire in Nov.Personnel Listed.Without Encls ML20206F0931999-04-30030 April 1999 Forwards LaSalle County Nuclear Power Station,Units 1 & 2 Effluent & Waste Disposal Semi-Annual Rept for 1998. LaSalle County Station Tech Specs Recently Revised to Reduce Periodicity of 10CFR50.36a ML20206D5921999-04-28028 April 1999 Forwards Annual Environ Operating Rept for 1998 for Environ Protection Plan, for LaSalle County Station,Units 1 & 2. Rept Includes Info Required by Listed Subsections of App B to Licenses NPF-11 & NPF-18 ML20206B2471999-04-20020 April 1999 Informs That SE Kuczynski Has Been Transferred to Position No Longer Requiring SRO License.Cancel License SOP-31030-1, Effective 990412 ML20205L8161999-04-0808 April 1999 Advises NRC of Util Review & Approval of Cycle 8 Reload Under Provisions of 10CFR50.59 & Transmit COLR for Upcoming Cycle Consistent with GL 88-16.Reload Licensing Analyses Performed for Cycle 8 Utilize NRC-approved Methodologies ML20205J9451999-04-0505 April 1999 Submits Petition Per 10CFR2.206 Requesting That LaSalle County Nuclear Plant Be Immediately Shut Down & OL Suspended or Modified Until Such Time That Facility Design & Licensing Bases Are Properly Updated ML20205K5841999-03-31031 March 1999 Submits Rept on Status of Decommissioning Funding for Reactors Owned by Comm Ed.Attachment 1 Contains Amount of Decommissioning Funds Estimated to Be Required Pursuant to 10CFR50.75(b) & (C) ML20205B4241999-03-23023 March 1999 Provides Results of drive-in Drill Conducted on 990208,as Well as Augmentation Phone Drills Conducted Since 981015,as Committed to in Util ML20207J9841999-03-0505 March 1999 Informs That Effective 990212,KC Dorwick Has Resigned & No Longer Requires Use of NRC License for LaSalle County Station ML20207F9581999-03-0101 March 1999 Requests That Initial License Examination Currently Scheduled for Weeks of May 15 & 22,2000 Be Changed to Weeks of Nov 13 & 20,2000.Class Size Is Projected to Be Twelve RO & SRO Candidates ML20207C7251999-03-0101 March 1999 Forwards Annual Rept for LaSalle County Station, for Period of 980101-981231.App E to Rept Provides Info on All Personnel Receiving Exposures of More than 0 Mrem/Yr Rather than 100 Mrem/Yr Requirement of TS 6.6.A.2 ML20207D6831999-03-0101 March 1999 Forwards fitness-for-duty Program Performance Data for Each Comed Nuclear Power Station & Corporate Support Employees for Six Month Period Ending 981231,per 10CFR26.71(d) ML20207C8401999-02-25025 February 1999 Forwards Rev 60 of Comed LSCS Security Plan,Iaw 10CFR50.4(b) (4).Rev Eliminates Requirement for Annual change-out of Vital & PA Keys & Locks & re-configuration of PA Fence Around North Access Facility.Rev Withheld ML20207A9361999-02-24024 February 1999 Forwards Rev 4 to Restart Plan,To Reflect Review,Oversight & Approval Process Necessary to Restart Unit 2.Review & Affirmation Process Will Focus on Station Capability to Support Safe Dual Unit Operations 1999-09-30
[Table view] Category:UTILITY TO NRC
MONTHYEARML20059H5321990-09-11011 September 1990 Requests Withdrawal of Application for Amend to Licenses NPF-11 & NPF-18,per 891215 & s.Amend Would Have Removed Applicability of Tech Spec (TS) 3.0.4 to TS 3.6.5.2, Secondary Containment Automatic Isolation Dampers ML20059H4271990-09-0707 September 1990 Provides Supplemental Response to NRC Bulletin 90-001.Plant Initial Review of Calibr Records Completed on 900831 ML20059G0941990-09-0505 September 1990 Forwards LaSalle County Station Unit 2 Third Refueling Outage,Asme Section XI Summary Rept for Spring 1990 Insp ML20059C6891990-08-30030 August 1990 Forwards LaSalle County Nuclear Power Station Unit 2,Cycle 4 Startup Test Rept & Test Rept Summary ML20056B4061990-08-21021 August 1990 Submits Supplemental Response to Generic Ltr 88-14 Re Design & Verification of Instrument Air Sys.Mfg Purchase Specs & Vendor Manuals Reviewed for Air Quality Requirements ML20059B8961990-08-14014 August 1990 Documents Approval of Schedular Extension & Accepts Human Engineering Discrepancies Discussed ML20059D1731990-08-10010 August 1990 Responds to NRC Re Exercise Weaknesses Noted in Insp Repts 50-373/90-05 & 50-374/90-06.Corrective Actions: LOA-FP-01, Fire Alarm Response Will Be Revised to Alert Control Room Operators to Refer to Emergency Action Levels ML20058N2971990-08-0606 August 1990 Forwards Rev 34 to Security Plan.Rev Details Addl Gate Position for Security Testing & Maint.Rev Withheld (Ref 10CFR73.21) ML20064A5491990-07-27027 July 1990 Responds to NRC Re Violations Noted in Insp Repts 50-373/90-12 & 50-374/90-13.Corrective Actions:Program Implemented Identifying & Correcting Repetitive Local Leak Rate Failures Through Testing & LER Investigation ML20056A7031990-07-27027 July 1990 Responds to NRC Re Violations Noted in Insp Repts 50-373/90-13 & 50-374/90-14.Corrective actions:LRP-1250-3 Revised to Include Addl Requirement for Extremity Monitoring ML20055H7631990-07-25025 July 1990 Forwards Financial Info Re Decommissioning of Plants ML20055H7661990-07-24024 July 1990 Forwards Supplemental Response to Generic Ltr 90-04, Status of Licensee Implementation of Generic Safety Issues Resolved W/Imposition of Requirements or Corrective Actions ML20055G2011990-07-13013 July 1990 Forwards Corrected Monthly Operating Rept for June 1990 for LaSalle County Unit 1.Outage/Reduction 16 Corrected ML20055F1831990-07-0909 July 1990 Provides Status Rept on Breaker Replacements in Response to NRC Bulletin 88-010.Breaker Replacements for Plants Scheduled to Be Completed by 901031 ML20044B1751990-07-0909 July 1990 Responds to NRC Request for Addl Info Re Util 890726 Proposed Amend to Tech Specs to Allow Continued Operation for Period of 12 H W/Main Steam Tunnel High Ambient Temp & High Ventilation Sys Differential Trips Bypassed ML17202L2861990-07-0202 July 1990 Forwards Dresden II Upper Vessel Contract Variation Review, La Salle II Upper Vessel Fabrication Summary & Quad-Cities II Upper Vessel Fabrication Summary. ML20055D1921990-06-29029 June 1990 Responds to Generic Ltr 90-04 Re Status of Licensee Implementation of Generic Safety Issues ML20055J2021990-06-26026 June 1990 Responds to NRC Re Violations Noted in Insp Repts 50-373/90-06 & 50-374/90-06.Corrective Actions:Perimeter Zone Repairs Commenced on Schedule & Completely Functional & Out of Compensatory Measures on 900614 ML20044A5071990-06-22022 June 1990 Forwards Revised Response to Station Blackout Rule for Plant.During Blackout Event,Plant Can Utilize RCIC Sys or HPCS to Provide Required Reactor Vessel Inventory Makeup ML20043E8651990-06-0707 June 1990 Forwards Relief Request RV-57 for Emergency Fuel Pool Makeup Crosstive Vent Valve 1(2)E12-F097.Expedious Review of Request Requested Because Valve 1(2)E12-F097 Inoperable & Will Remain So Until NRC Approval Received ML20043D3221990-06-0101 June 1990 Forwards Rev 33 to Security Plan.Rev Withheld (Ref 10CFR73.21) ML20043C8241990-06-0101 June 1990 Advises of Intentions to Review & Approve Cycle 4 Reload,Per 10CFR50.59 & Forwards Rev 1 to LAP-1200-16, Core Operating Limits Repts for LaSalle County Station Unit 2,Reload 3, Cycle 4, Per Generic Ltr 88-16 ML20043B6581990-05-25025 May 1990 Requests Schedular Extension of Two Human Engineering Deficiencies Re CRT Displays W/Current Ramtek Sys & Approval to Leave Seven Human Engineering Discrepancies Accepted as Is. ML20043B7921990-05-23023 May 1990 Forwards Endorsements 14 to Nelia Policy N-71 & Maelu Policy M-71 & Endorsements 12 to Nelia & Maelu Policies N-83 & M-83,respectively ML20042E8841990-04-30030 April 1990 Responds to Generic Ltr 89-04 Re Weaknesses of Inservice Testing Programs.Plant Has Implemented Rev 2 of Inservice Testing Program Submitted by Util 891002 & 24 Ltrs.No Equipment Mods Required as Result of Generic Ltr ML20042F3591990-04-29029 April 1990 Provides Suppl Response to NRC Bulletin 88-004, Potential Safety-Related Pump Loss. Precaution Added to Operating Procedures Which Allows ECCS Pump to Be Secured & Restarted as Necessary to Preclude Running Pumps at Min Flow ML20042F0341990-04-23023 April 1990 Forwards Part 3 to 1989 Operating Rept,Containing Results of Radiological Environ & Meteorological Monitoring Programs. W/O Encl ML20064A6281990-03-30030 March 1990 Submits Supplemental Response to Insp Repts 50-373/86-04 & 50-374/86-04 Re Fire Detection Concerns,Per NRC 900214 Request.Proposed Administrative Controls & Training Will Eliminate Concerns That Assure Protection of Personnel ML20055E1461990-03-29029 March 1990 Provides Supplemental Response to Re Violations Noted in Insp Repts 50-373/89-18 & 50-374/89-18 on 890724- 0825.Corrective Actions:Plant Performs Safety Evaluation for Mods Not Designed by Corporate Nuclear Engineering Dept ML20012C6991990-03-15015 March 1990 Forwards Corrected Tech Spec Page to 881129 Application for Amend to Licenses NPF-11 & NPF-18,removing Specific Load Profiles for Each Dc Battery ML20012B6541990-02-26026 February 1990 Forwards LaSalle County Station Unit 1 Third Refueling Outage ASME Section XI Summary Rept, for Fall 1989 Inservice Insps Performed.Conditions Observed & Corrective Measures Taken Also Contained in Rept ML20006E7421990-02-0909 February 1990 Responds to NRC 900110 Ltr Re Violations Noted in Insp Repts 50-373/89-23 & 50-374/89-22.Corrective Actions:Ltr from Station Manager to All Dept Heads Was Issued on 891218, Discussing Personnel Performance Issues ML20005F5771990-01-0808 January 1990 Documents Guidance Given by P Shemanski Re Typos in Earlier Approved Amend to License NPF-11.Guidance Should Adhere to Wording of Unit 2 Tech Specs.Guidance Given on 900105 & Will Be Followed Until Correction Made at NRR Ofcs ML20011D9661989-12-22022 December 1989 Forwards Core Operating Limits Rept for LaSalle County Station Unit 1,Reload 3 (Cycle 4). Intention to Review & Approve Cycle 4 Reload Under Provisions of 10CFR50.59 Stated ML20005E1661989-12-22022 December 1989 Forwards Rev 32 to Security Plan,Reflecting Administrative Changes in Mgt Structure at Facilities.Rev Withheld (Ref 10CFR73.21) ML19332E4531989-11-29029 November 1989 Responds to Generic Ltr 89-21, Status of Implementation of USI Requirements. Response to USI A-48 Expected by 900319 ML19332C2461989-11-0808 November 1989 Provides Supplemental Response to Insp Repts 50-373/88-05 & 50-374/88-05 on 890302-10.Scheduled Completion Dates for Sample Panel Mods Changed from Third to Fourth Refueling Outages of Each Unit ML19325E5191989-10-31031 October 1989 Forwards Qualification Test Rept QTR87-018, Max Credible Fault Tests CM249-Q2 Carrier Modulator for Fermi 2 SPDS, in Response to NRC 890304 Request for Addl Info Re Facility Validyne Isolator CM-249 ML19325E3601989-10-26026 October 1989 Forwards Addl Info Re Application for Amend to Licenses NPF-11 & NPF-18,revising Tech Specs to Conform W/Diesel Generator Test Schedule Recommendations,Per Generic Ltr 84-15 ML19325E7921989-10-24024 October 1989 Submits Response to SALP 8 Board Repts 50-373/89-01 & 50-374/89-01.Expresses Appreciation for NRC Recognition of High Level of Performance in Area of Plant Operations, Emergency Preparedness & Security ML19325E0941989-10-24024 October 1989 Forwards Clarification to Summary of Changes Made in Rev 2 to Plant Inservice Testing Program ML19353A9051989-10-23023 October 1989 Responds to NRC 890921 Ltr Re Violations Noted in Insp Repts 50-373/89-19 & 50-374/89-19.Corrective Actions:Hose Connection That cross-connected Svc Air Sys W/Clean Condensate Sys Uncoupled & Secured ML17285A8081989-10-18018 October 1989 Responds to Request for Info on Environ Qualification of Taped Electrical Splices.Scotch Tapes Allowed by Electrical Test Guide Included Scotch 33,23 & 70 ML19325D1931989-10-13013 October 1989 Forwards Quarterly Rept on Static-O-Ring Failures Third Quarter 1989,per IE Bulletin 86-002.Stated Switches Replaced ML19327B0431989-10-0505 October 1989 Responds to NRC 890821 Ltr Re Violations Noted in Insp Repts 50-373/89-15 & 50-374/89-15.Corrective actions:post-order for Assembly Revised to Provide Specific Guidance on Use of Siren & Loudspeaker on Mobile Vehicles During Assemblies ML19327A7491989-10-0202 October 1989 Forwards Rev 2 to Combined Units 1 & 2 Inservice Testing Program for Pumps & Valves. Implementation of Program Will Require Procedure Revs Expected to Be Completed by 900228 ML19325D3271989-10-0202 October 1989 Forwards Rept Re Findings & Conclusions of Investigation Re 890826 Scram ML20248D0881989-09-21021 September 1989 Forwards Rev 56 to QA Program Topical Rept CE-1-A ML20247Q6431989-09-21021 September 1989 Documents Relaxation of Commitment Re Disassembling & Insp of Sor Switches ML19327A7681989-09-18018 September 1989 Forwards Response to Allegations Re Potential Employment Discrimination.Encl Withheld (Ref 10CFR2.790(a)(7)) 1990-09-07
[Table view] |
Text
"a , Commonwealth Edison
, *4 One First National Plaza, Chicago, Illinois Address Reply to: Post Office Box 767 Chicago, Illinois 60690 January 12, 1979 Mr. O. D. Parr, Chief Division of Project Management Nuclear Regulatory Commission Washington, D.C. 20555
Subject:
Caseload Forecast Panel Update of the LaSalle County Station Unit 1 Fuel Load Date NRC Docket No. 50-373 Reference (a) : O. D. Parr letter to L. O. DelGeorge dated 12/20/78
Dear Mr. Parr:
Enclosed are responses to the Construction Forecast Panel questions relative to LaSalle County Unit 1, transmitted to Commonwealth Edison in Reference (a). We appreciate this opportunity to review with you the construction progress on this project since August 1978, which has been significant notwith-standing a work stoppage in September 1978 due to a union strike.
The LaSalle Unit 1 fuel load is projected by Commonwealth Edison to be July 1, 1979. This represents an adjustment of approximately 3 months from the previously projected March 30, 1979 fuel load date. This adjustment can be attributed to (a) the impact of the September 1978 Boilermaker's strike; and (b) the design change to incorporate KWU quenchers. The replacement of the reactor recirculation inlet thermal sleeves and safe-ends, although not expected to impact the July 1, 1979 schedule, also contributed to the decision to reassess the March 1978 date.
The September strike impact caused a three week actual working time loss plus a lingering craft manpower shortage problem which extended through December. Mechanical and electrical installation quantities prior to the September strike were keeping pace with those necessary to meet the March 1979 fuel load date.
Mechanical installation quantities reached pre-strike quantities in early December and are still rising. Electrical installation
\
1
\
4)(/\
\
79011704 W A
Commonwealth Edison NRC Docket No. 50-373 Mr. O. Parr: January 12, 1979 quantities are fast approaching the pre-strike quantities. A more complete summary of the actual quantities involved are provided in the responses to the referenced forecast panel questions.
The impact of the KWU Quencher and reactor recirculation changes will be amplified in the answers to Questions 8 and 9.
Since the August 1978 NRC site visit, several major milestone activities have been completed. The Reactor Pressure Vessel Integrated Flush was completed September 6, 1978. During the week of December 24, 1978, the Primary Containment Structural Integrity Test was successfully completed. Fuel receipt commenced on January 3, 1979. All activities were completed as scheduled.
In light of these accomplishments, it is important to recognize that the July 1, 1979 fuel load date identified in this letter does not only represent a construction projection but rather a primary objective of the Commonwealth Edison Company. Every effort is being made to preserve the viability of that date including necessary commitments of manpower and money. Although the July 1, 1979 schedule is admittedly optimistic when viewed in the light of average performance within the nuclear industry, it is our firmly held judgement that July 1, 1979 can be achieved by Commonwealth Edison barring some currently unforeseen event (s) and assuming continued performance both on and off the job site at levels currently achievable. We do not, however, minimize the magnitude of the task; it is in fact judged that slippages in material deliveries could impact the July 1, 1979 date. In addition, our ability to integrate the preoperational test program with on-going construction activities may impact the July 1, 1979 date. However, our experience in the construction management and startup of seven previous nuclear units convinces us that the uncertainty associated with the July date is no greater than two months. For this reason, we must take strong exception to the current NRC forecast date for LaSalle Unit 1 of December 1979 which we believe does not give due consideration to this utility's previous experience As has been stated, we appreciate this opportunity to review with you the on-going construction activities on LaSalle County Unit 1. Detailed responses to the questions contained in Reference (a) are enclosed as an attachment to this letter. In the event you have any further questions, please direct your
Conunonwealth Edison NRC Docket No. 50-373 Mr. O. Parr: January 12, 1978 inquiry to this office. As has been discussed with Mr. A. Bournia of your Staff, we will be available to review the information presented herein with your Staff on January 23, 1979 in the event you are unable to agree with the July 1, 1979 fuel load date projected by Commonwealth Edison for LaSalle County Unit 1.
Very truly yours, 7l
. /[ - n4 Cordell Reed Assistant Vice-President enclosure 4
. . Commonwealth Edison NRC Docket No. 50-373 ENC LOSURE Response to NRC Construction Forecast Panel Questions - LaSalle Unit 1 Question 1: General Electric Stress Report General Electric's Stress Report was released in October 1978.
Question 2: Hanger Design Status out of a total of 11,600 hangers on Unit 1, approximately 900 hangers have not been released for fabrication. About 100 of these hangers are on the safety / relief valve (S/RV) discharge lines in the supprcssion pool which is a new design. We expect release of the S/RV hangers by 2/1/79, with release of all hanger by 3/1/79.
Question 3a: Large Bore Piping Of the 8,809 Unit 1 spools required for commercial operation, 8,590 spools or 98% are installed. Essentially large bore piping work is complete. The remaining spools fall in three categories. The first category represents major design changes where existing installed spools are being replaced. These changes are primarily in the heater drain and main steam safety valve discharge piping systems. This category represents 139 spools.
The heater drain piping change installation work is in progress.
The main steam safety valve discharg piping installation work will start March 1, 1979 with completion in May 1979. The second category represents 36 permanent spools which are required as replacements for temporary piping spools installed for design tests or flushing operations. These flanged spools will be installed as required in accordance with preoperational test program needs. The thrid category represents 43 spools. These spools are being withheld to facilitate construction access. Again, these spools will be installed as required for preoperational test program needs.
Question 3b: Small Bore Piping Approximately 69,000 lineal feet out of 256,000 lineal feet of 2" and under piping and instrumentation piping remain to be installed. Current installation rates of 16,000 lineal feet per month indicate a completion data of May 1. Since a portion
Commonwealth Edison imC Docket No. 50-373 of this piping is for equipment drain'., it is expected that all 2" and under piping, required for preop. testing, will be complete near April 1. Based on our current status, it is also expected that installation activity can casily be sequenced to permit preop. testing on many systems prior to the completion of 2" and under piping.
Question c: Hanger / Snubber Installation The estimated total of hangers and snubbers yet to be installed is 4,000 (includes those yet to be released for fabrication and delivered). Over 60% of this total are seismic restraints which do not significantly impact the preop. test program. The remaining supports are expected to be installed by May 1979. All hanger erection is currently being sequenced with preoperation test schedule requirements to avoid delays in the test program.
Question 3d: Hanger / Snubber Fabrication & Delivery The estimated total of hangers and snubbers remaining to be shipped to site (including those still to be released for fabrication)is 3,000. The estimated total number of hangers /
snubbers / restraints required for Unit 1 is 11,600 Based on current manufacturing information, all supports should be shipped by March with the possible exception of the main steam relief valve line supports which may not be complete entil April.
Question 3e: Cable Installation The current number of estimated cables for Unit 1 is 15,500. As of December 1978, 9,824 cables have been pulled, leaving 5,676 to be pulled by May 1979. This will require that approximately 1,500 cables be pulled por month. In August 1978, 1,435 cables were pulled. In December 1978, the two week average prior to the holidays was 400 cables per week, with a total of slightly over 1,000 cables pulled in December. With the current manpower allocation, it is judged that cable pulling rates of 1500/ month are now readily achievable. This fact combined with sequential pulling of cables by system, insures that the preoperational test program can proceed on its current schedule.
Question 3f: Cabic tray Installation Cable tray installation in all Unit 1 builing is substantially complete. In this regard, unless other critoria
Commonwealth Edison Imc Docket No. 50-373 need to be addressed it is judged that the fire protection audit for this site should now be scheduled. Mr. Bournia of your Staff informally identified 90% of cable trays installed as the controlling prerequisite for such an audit.
Question 3g conduit installation continues to be the highest electrical schedule priority. As of January 1, 48,380 lineal feet of conduit representing 36% of the total Unit 1 footage remains to be installed. The current installation rate continues to rise based on increased production due to the night shift. In addition, the remaining conduit is comprised of the smaller sizes which will contribute to higher production totals over the next three months. All Unit 1 conduit is scheduled to be completed April 1, 1979.
Question 3h: Cable Terminations currently 13,583 terminations have been completed representing 45% of the estimated total 31,000 terminations required for Unit 1. The termination work continues to closely track the cable pull rates, thus indicating no significant schedule problems in this area.
Question 4a: Draft Preoperational Test Procedures All 107 draft preoperational test procedures are completed.
Question 4b: Draft Preoperation Test Procedures Issued for Comment only one (1) draft preoperational test procedure out of 107 procedures remains in the issued for comment stage.
Question 4c: Preoperation Test Procedures in Final Preparation Currently, forty-five (45) preoperational test procedures are in the final preparation stage. Fifteen (15) procedures are in final typing, twenty-five (25) are in the LaSalle County on-site approval chain and five (5) are in final draft preparation.
These 45 procedures will have final engineering approval by March 1, 1979.
Commonwealth Edison NRC Docket No. 50-373 Question 4d: Engineering Approval of Preoperationah Test Procedures Ten (10) preoperational test procedures are currently in engineering for approval.
Question 4e: Preoperational Test Procedures Approved Fifty-one (51) of 107 preoperational test procedures are approved.
Question 4f: Preoperational Tests Completed As of December 31, 1978, no preoperational tests are 100%
complete and released for operation. Several tests are more than 75% complete (see response to Question 4g).
Question 4g: Preoperational Tests in Progress As of December 31, 1978, thirteen (13) preoperational tests are ongoing. The rate of system turnover and test performance is accelerating. The current schedule shows preoperational testing performance is keeping pace with the requirements necessary to meet the currently projected fuel load date. It is worth noting that a significant number of systems have been flushed 65% and also hydroed. This fact contributes to the judgement that the completion of preops will accelerate over the coming months.
Question 5: Overall Percent Complete The overall Unit 1 completion percentage as of December 31, 1978 is 81%.
Question 6: Turbine Shield Wall Concrete Turbine shield wall concrete formwork is in progress.
Current plans are to complete the concrete pours the week of February 19, 1979.
Question 7: Cable Pulled Per Month Since 8/1/78 The lineal feet of cable pulled per month since August 1, 1978 is as follows:
Commonwealth Edison NRC Docket No. 50-373 Month Lineal Feet Pulled August 1978 426,653 September 1978 50,040 (Boilermaker Strike)
October 1978 191,498 November 1978 243,966 December, 1978 270,344 During September 1978, the project was shut down by a boilermaker's strike. Essentially, the above quantities of cable pulled represents only 3 1/2 months of productive pulling work -- the balance of the time being the strike and strike recovery period. The lineal feet of cable pulled per month will continue to increase as the cables per month increase. Cable pulling is being sequenced to support the preoperational test program requirements.
Question 8: Replacement of Thermal Sleeves and Safe-Ends As stated earlier, the replacement of the thermal sleeves and safe-ends contributed to the three month delay in the March 1979 fuel load date. This modification work is not the schedule controlling factor and will be completed prior to the July 1, 1979 projected fuel load date. It is important to note that the recirculation pipe which was scheduled for initial cutting on 2/1/79 has been rescheduled for cutting on 1/20/79. Full scale mock-up tests of the tooling involved was conducted during the week of 1/8/79. All prerequisite engineering is complete. This job is proceeding ahead of schedule.
Question 9: Mark II Containment Schedule Impact The decision to install the KNU Quencher design was perhaps the greatest contributing factor to the three month delay in the March 1979 fuel load projected date. Expediting of support design for the main steam relief valve piping and delivery of the quenchers is receiving the highest priority. Work has
Commonwealth Edison NRC Docket No. 50-373 started in the Suppression chamber for quencher supports in the basemat. The quencher supplier has committed to complete equipment deliveries by March 24, 1979. All associated S/RV piping spools are currently in fabrication and are scheduled for initial delivery to the site by 2/1/79. All remaining hangers (see question 2) will be released for fabrication by 2/1/79.
Although it is recognized that the completion of this work as scheduled will be a major accomplishment, present hardware commitments indicate that this work should be completed prior to the July 1, 1979 projected fuel load date.