ML19263E759

From kanterella
Jump to navigation Jump to search
Submits Followup to in Response to IE Bulletin 79-03.Ultrasonic Examination Evaluation Indicates Acceptance Stds of Section III of ASME Code,1971 Edition,Are Acceptable
ML19263E759
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 05/16/1979
From: Jeffery Grant
TOLEDO EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
NUDOCS 7906250140
Download: ML19263E759 (1)


Text

/{ h

.,;. ah' TOLEDO

%ss EDISON JAMES S. GRANT Docket ho. SL-346 l;','g,"4,[,'

License No. NPF-3 Serial No. 1-70 May 16, 1979 Mr. James G. Keppler Regional Director, Region III Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137

Dear Mr. Keppler:

This letter is submitted as a follow-up to our letter (Serial No. 1-57) of April 16, 1979 concerning IE Bulletin 79-03.

As stated in our letter of April 16, 19 '. ultrasonic examination revealed indications which required evaluation in terms of the acceptance standards of NE-5330 of the ASME Code,Section III.

As a result of this evaluation, it has been determined that the indications do not exceed the ultrasonic acceptance standards of Section III of the ASME Code, 1971 Edition.

Our letter of April 16, 1979 also indicated thtt indications were not found in the 8 feet of spool 34-HCB-4-4 examined. This statement is in error as one recordable indication was found in the portion of this spool examined.

As stated in the previous paragraph, this indication was acceptable to the requirements of ASME Section III.

Yours very truly, JSG:CTD cc: