Postpones from 781116 to 781214 the Due Date for Next Rept on Deficient Reactor Coolant Pump Tie Rod Embedments
ML19263B903
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 11/17/1978
From: Gilleland J
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
NUDOCS 7901250118
Download: ML19263B903 (1)


Text

/

Y '

^/_y y/

TENNESSEE VALLEY AUTHORITY ,M cn ATT A noco6 pNNCSSc E. ap108

.,.  :,y 830 Power BuildIn?,'iC.l,i

' U N 0!/ ((J $'/g l.7 38 .

Mr. James P. O'Reilly, Director Office of Inspectton and Enforcement U.S. Nuclear Regulatory Commission Region II - Suite 3100 101 Marietta Street Atlanta, Georgia 30303

Dear Mr. O'Reilly:

SEQUOYAH NUCLEAR PLA';T UNITS 1 AND 2 - REACTOR C001. ANT PUblP TIE ROD D13EDMENTS - liCR SQN-002 The subject deficiency was initially reported to NRC-0IF. Inspector J. K. Rausch on May 9, 1978. Our letter to you u. June 9, 1978, stated that our next report would be submitted on November 16, 1978.

As agreed in our telephone convernation with V. Brownlee on November 15, 19'/8, this report will be submitted on December 15, 1978.

If you have any questions concerning this matter, picane get in touch with M. R icenhurg at FTS 854-2581.

Very truly yours, t

, k t 'h, t*f

'J . E. Gilleland Asnistant flanager of Power cc: Mr. John G. Davis, Acting Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Conr.aission Washington, DC 20555 7901250112 3