ML19263B004

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-348/78-29 on 781017-20.No Noncompliance Noted.Major Areas Inspected:Licensee Event Repts,Ie Bulletins & Circulars,Review & Audits,Inspector Identified Items
ML19263B004
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 11/15/1978
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19263A995 List:
References
50-348-78-29, NUDOCS 7901040034
Download: ML19263B004 (5)


See also: IR 05000348/1978029

Text

.

.

.

UNITE D sT ATEs

alcg

m

[g a

'o,

NUCtE AR REGULATORY COMMISSION

[}

," k

RE GloN il

.,

E

230 PE ACHTREE sTnF ET N W SUITE 1217

2

  • -

x

} }k

[

ATL ANT A GE ORGI A 30303

o

%, .....f

Report No.

50-348/78-29

Docket No.

50-348

License No.

NPF-2

Licensee:

Alabama Power Company

Post Office Box 2631

Birmingham, Alabama 35291

Facility Name

Farley l' nit-1

Inspection at:

Farley Site, Ashford, Alabama

Inspection Conducted:

October 17-20, 1978

Inspector:

A. K. Hardin

Accompanying Personnel:

None

Approved by:

/

6-

r&M _

//[/ 5[7[

R . C . Lew i's , C h i e f

Date

Reactor Projects Section No. 2

Reactor Operations and Nuclear Support

Branch

Inspection Summary

Inspectson on October 17-20

1978 (Report No. 50-348/78-29):

2

Areas Inspected:

Routine , unannounced inspe ction of licensee event

reports, IE Bulletins and circulars, review and audits, and inspector

identified items.

The inspection involved 26 man-hours on-site by one

NRC inspector.

kysuIts:

Of the four areas inspected, no items of noncompliance or

deviations were identified.

790104003f

.

.

.

RII Rpt. No. 50-348/78-29

-1-

DETAILS I

Prepared by: h

_ (3 b

//

&

A. K. Kardin, Reactor Inspector

Date

Reactor Projects Section No. 2

Reactor Operations and Nuclear

Support Branch

Dates of Inspection: October 17-20, 1978

Reviewed by.

86

/h.[5 /[

R. C. Lewis, Chief

Date

Reactor Projects Section No. 2

Reactor Operations and Nuclear

Support Branch

1.

Persons Contacted

  • W.

G. Hairston, Plant Manager

kJ. D. Woodard, Assistant Plant Manager

  • D. N. Morey, Maintenance Supervisor

23. R. Campbell, Manager, Operations Qaality Assurance

  • D. L. Cox, Operations Quality Assurance
  • J. W. Kale, Operations Quality Assurance
  • F. Wurster, Operations Quality Assurance

T. C. Grozan, Plant Engineer

D. C. Poole, Operations Superintendent

L. W. Enfinger, Document Control Supervisor

D. E. Mansfield, Startup Superintendent

L. E. Ward, Startup Supervisor

  • Denotes those present at the Exit Interview.

2.

Licensee Action on Previous Inspection Findings

Not applicable.

3.

Unresolved Items

None were identified during this inspection.

4.

Exst Interview

An exit laterview was held at the conclusion of the inspection on

October 20, 1978, with Mr. W. G. Hairston and other members of

Alabama Power Company as identified by an asterisk in paragraph I.

The scope and findings of the inspection were discussed.

.

.

,

RII Rpt. No. 50-348/78-29

-2-

5.

Review and Audits

Selected minutes for both the on-site safety review committee and

the off-site safety review committee were reviewed to ascertain

that meetings had been held at the required frequency, that a

quorum was present, and that appropriate items as specified in the

technical specification were being reviewed.

The records reflect that + ring a 12-month period (from October 28,

1977 to November 1, 1978), more than eighty meetings of the Plant

Operations Review Committee (PORC) were conveneo.

Attendance at 30

of these meetings was noted.

No areas of noncompliance were identi-

fied in meeting frequency and agenda items for the on-site safety

committee. Selected meeting minutes for the Off-site Safety Committee

(NORB) were reviewed. These included minutes 77-5 through 77-12,

plus the minutes of 78-1 and 2.

No areas were identified where

meeting frequency, quorum requirements, and subjects reviewed were

not met as required by technical specifications.

At the exit

interview, the inspector questioned the timeliness of reviews of

licensee event reports (LER's) by the NORB, and that reports such

as LER 77-24 was listed as being reviewed in NORB minutes 78-1 of

March 15, 1978.

LER No. 77-24 is dated September 28, 1977,

The

licensee stated the scheduled meetings of the NORB were every six

months and that their review of LER's was considered timely on that

basis.

The inspector stated the item would be left open pending an

in-office review of the LER's which had been reviewed by the NORE.

An in-office review was conducted on October 25, 1978. The timell-

ness of review of 30-day licensee event reports by the off-site

NORB Committee was concluded to meet regulatory requirements.

6.

IE Bulletin 78-10

IE Bulletin 78-10 entitled "Bergen-Patterson Hydraulic Shock Suppressor

Accumulator Spring Coils", described a problem with broken spring

coils on early model BP suppressors.

The licensee was directed to

take corrective action if the affected models were installed or in

stock and to describe the condition of the springs.

The licensee

responded on July 17, 1978, that their review confirmed that no

such equipment is used or planned for use at the Farley Nuclear

plant.

On this inspection, the inspector reviewed the document

file on IE Bulletin 78-10.

Records indicate the storekeeper has

reviewed inventory files and has determ.ned there are no snubbers

of the type described in stock.

A letter in the file, from Bechtel

to Southern Company Services, states that there are no Bergen-

Patterson suppressors at Farley.

All suppressors are manufactured

by Grinnell.

The inspector had no further questions.

.

RII Rpt. No. 50-348/78-29

-3-

'

7.

IE Circular 78-09

IE Circular 78-09, entitled " arcing of General Electric Company

NEMA Size 2 Contsctors" described a prob.em with binding in the

contactor, resulting in arc-burn damage. The licensee was advised

to determine if the type contactor in question was installed or if

there are some in spare parts at their plant action in which case

appropriate corrective action would have to be taken.

The inspector

verified (through record review) that Bechtel, Southern Company

Services and the plant had determined that no contactors of the

type described were installed in safety systems, nor were there any

in spare parts inventory.

8.

Open Items

78-09-04

" Sequence Failure BIG Diesel"

a.

The subject open items dealt with failure of an Agastat relay

in the BlG diesel sequencer. On the current inspection, a

sequencer cabinet and the installed Agastat relays were inspected.

The sequencer and reliability of the system were discussed

with a licensee representative.

At the exit interview, the

inspector stated there were no further questions and item

78-09-04 would be closed.

b.

78-17-01 - Installation of Stem Mounted Limit Switches

In response to IE Bulletin 78-04, the licensee had determined

that some stem mounted limit switches inside containment were

not environmentally qualified.

The current status of correction

of this problem was reviewed.

The licensee has purchased sufficient numbers of switches to

replace all of the nonqualified switches; however, the vendor

could only supply one type of mounting in the environmentally

qualified switch.

The licensee stated they were able to

replace six switches directly during the September 1978 outage,

but that revisions would be required to the switch mounting in

order to install the remaining (about 80) switches.

The

licensee stated Bechtel has been requested to provide a design

for mounting of the switches and that the goal for replacement

is during the refueling outage scheduled for April 1979.

The

switches in question all provide valve position indication,

according to the licensee. This item remains open.

.

.

.

RII Rpt. No. 50-348/78-29

-4-

9.

Licensee Event Report (LER) Revieu

The inspector performed an in-office review of the reportable

occurrences listed below to verify that the report details met

license requirements, identified the cause of the occurrence,

described corrective actions appropriate for the identified cause,

and adequately assessed the occurrence and any generic implications.

In addition, follow-up review at the site was conducted by examining

logs, records and internal incident reports and by interviewing

personnel to verify the report accurately reflected the circumstances

of the occurrence, that corrective action had been taken or responsi-

bility assigned to assure completion, that any violation of regula-

tions or license conditions had been identified and that the occur-

rence was reviewed as required by Technical Specifications.

Unless

otherwise stated, the event reports are closed.

LER 78/54/03, " Damaged RCP Undervoltage Relay"

a.

b.

LER 78/55/03, " Loss of IB Startup Transformer and Failure

of IB Diesel Generator to Close on 4160V Bus Automatically"

Review of this LER at the site indicated that the stated cause

of failure of the IB DG to close on the 4160V bus may not have

been the initial cause of failure. The stated cause in the

LER was that the operating mechanism for the auxiliary contacts

were out of alignment.

In discussions with a licensee represen-

tative, the inspector concluded that the originating cause may

have been a faulty contact in an Agastat relay.

At the exit

interview, this apparent discrepancy was discussed by the

inspector.

This item will remain open, pending further review

by the inspector (78-29-01).

LER 78/56/03, "T Average Decrease Below T.S. Limits"

c.

d.

LER 78/57/03, " Failure of Surveillance Test on Containment

Air Lock Door Seal"

LER 78/58/03, "Tavg Decrease During Change _F_ rom Main-Feed

e.

to_ Auxiliary Feed System"

f.

LER _78159f 03, "Tavg increase During Rapid Load Reduct_i_cn"

g.

_LER 78/60/03

"DG,-2C_ Speed Control Potentiometer Failure *f

3

h.

LER_ 78/61/03, "DG l-2A Speed Control Potentiometer"

.

.

.

RIl Rpt. No. 50-348/78-29

-5-

i.

LER 78/62/01, " Missing Seismic Restraint"

10.

Current Tra ns f o rmers

During testing of Unit 1, current transformers for the 4160 switch-

gear did not meet saturation and resistance valves claimed by the

manufacturer.

The licensee determined that the transformers were suf ficiently

accurate to monitor the maximum current carrying of the switch gear

and that the nameplates should be changed to the saturation and

resistance curve valves which can be accurately read by the trans-

formers. The inspector discussed this item with licensee represent-

ative and inspected current transformer installations at Unit 2.

There were no further questions on this event.

11.

Diesel Generators - Part 21 Reports

a.

Possible Rocker Arm Defect

On September 26, 1978, Fairbanks Morse-Engine Division informed

the NRC of a possible defect in exhaust rocker arms of their

Model PC-2 diesels.

A copy of their report was transmitted to

the Farley Plant Manager, advising that an inspection / corrective

action plan was being developed for Farley Units 1 and 2, who

have three of the PC-2 diesels.

On the current inspection,

the licensee stated they expected to receive from Fairbanks

Morse a proposed inspection procedure within 10 days.

Following

review by the licensee, the actual inspection is ant 2cipated

to be done in late November 1978 (78-29-02).

b.

Potential Fuel Injection Pump Failure

On September 22, 1978, the NRC was notified by Fairbanks Morse

of a potential fuel injection pump failure due to seizing of

the pump plunger to the pump barrel.

The licensee stated they

had discussed the problem with Fairbanks Morse and had reviewed

the potential for failure on the Farley diesels.

A review had

been made of startup test documentation and documentation

related to preventative maintenance performed during 1978.

No

problems or failures had been experienced with fuel injection

Tests have also been run on the 1B diesels to detect

p ump s .

defective fuel injection pumps by means of lowered cylinder

exhaust temperatures.

No failures were indicated, except

a

t he rmoc oupl e in cylinder number 12 was defective.

Further

tests are planned by the licensee

The item remains open

(78-29-03).