Metropditan Edison Company 6
Post Othee Box 542 Reading Pennsylvania 19640 215 929-3601 Writer's Direct Dial Number December 5, 1979 GQL 1h67 Director of Nuclear Reactor Regulation Attn:
R. W. Reid, Chief Operating Reactor Branch No. h U. S. Nuclear Regulatory Commission Washington, D. C.
20555
Dear Sir:
Three Mile Island Nuclear Station, Unit I Operating License No. DPR-50 Docket No. 50-2S9 Moderator Dilution Accicents This letter is in response to a telecon with Mr. DiIanni of your staff on November 21, 1979 Specifically, Mr. DiIanni requested Met-Ed to verify that all potential pathways for initiation of a moderator dilution accident have been reviewed and that both manual valves, one upstream and one down-stream of the ES-accuated valve, are closed prior to inservice inspection testing of the ES valve.
In response to the first request, Met-Ed has reviewed all potential pathways for initiation of a moderator dilutica accident (other than those listed in the TMI-1 FSAR and the Sodium Hydroxide injection) and discovered no other mechanism.
Ccncerning the second item for discussion, Met-Ed's procedures require both manual valves, which bracket the ES-operated valve, to be closed prior to testing the motor-operated valve, thus preventing e, moderator dilution accident occurring due to a failure of one of the manual valves.
Sincerely,
,/
r/.
N
- u. G. Herbain
['
Vice President Nuclear Operations 1 5 c,z, 1 2 0 f
JGH:DGM:bw 7 91210 0 3 A #
A0 1
5
./.
/f ss MetropoLtan Ecson Company :s a Merrter of me Genera! Pubec Ut!it es System