ML19262A117
| ML19262A117 | |
| Person / Time | |
|---|---|
| Site: | Crane |
| Issue date: | 09/25/1979 |
| From: | Herbein J METROPOLITAN EDISON CO. |
| To: | Grier B NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| References | |
| GQL-1191, NUDOCS 7910260375 | |
| Download: ML19262A117 (2) | |
Text
A WR gy 4
yf g
Metropolitan Edison Company e
f Post Office Box 542 y'J Read.'ng Pennsylvania 19640 a
215 929-3601 Writer's Direct Dial Number September 25, 1979 GQL 1191 Office of Inspection and Enforcement Mr. B. H. Grier, Director Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Trussia, Pennsylvania 19h06
Dear Sir:
Three Mile Island Nuclear Station, Unit 1 Operating License No. DPR-50 Docket No. 50-289
Reference:
Letter dated September 10, 1979, from J. G. Herbein (Met-Ed) to B. H. Grier (NBC)
Per the above referenced letter, we are submitting the attached schedule listing for the planned submittal date of all I&E Bulletins, received prior to this letter, which normally required action but were for our information only.
Included in this list are the dates and GQL numbers of letters which already responded to I&E Bulletins.
As stated in the referenced letter, we vill respond to I&E Bulletins in a tinely fashion.
Sincerely
)
8#
/
J. G. Herbein Vice President Nuclear-Operations JGH:DGM:mrm Attachment 1217 094 Metrepottan Fdson Comp ini.s a f,' mtx;r of the Cureral Put!:c Ut
- cs Symrn 7 91026037 F
- psY
4 IE BULL JIN SCHEDULE DATE TO BE DATE GQL NO.
SUBMITTED SUEMITTED NO.
CCSENTS 79-01 06-07-79 0482 completed 79-01A 9-28-79 79-02,02(1) 1-31 80 07-09-79 0882 Additional submittals planned 79-03 10-15-79 OL-13-79 0465 Additional submittal due 79-04 05-01-79 0611 completed 79-05, 05A, These bulletina vill be 05B, OSC addressed, as part of the TMI-1 restart package 79-06, 06A, Does not apply 06B 79-07 07-03-79 0866 Completed 79-08 Does not apply 79-09 06-27-79 0669 completed 79-10 07-05-79 0831 Completed 79-11 07-06-79 0880 completed 79-12 Does not apply 79-13 12-15-79 79-14 1-31-80 08-2h-79 1092 Additional cutmittals planned 79-15 10-31-79 79-16 09-13-79 1175 Completed 79-17 08-15-79 1059 Additional submittals planned 79-18 11-30-79 79-19 9-28-79 79-20 Does not apply 79-21 11-30-79 79-22 Does not apply 79-P3 10-31-79 Submittal planned in accordance with Bulletin 1?!7 095