Supplements Response to IE Bulletin 79-07, Seismic Stress Analysis of Safety-Related Piping. Amends Phase 3 Program for Reanalysis & Mod of Supports,Nozzlers & Penetrations After Entering Mode 2
ML19262A072
Person / Time
Site: Salem PSEG icon.png
Issue date: 10/18/1979
From: Librizzi F
Public Service Enterprise Group
To: Schwencer A
Office of Nuclear Reactor Regulation
References
NUDOCS 7910260304
Download: ML19262A072 (6)


Text

PW en cs

-iO PSEG PuCLc Service E!ecmc anc Gas Comoany 80 Park P' ace Newark, N a 07101 Pncne 201430-7000 October 18, 1979 Mr. Albert Schwencer, Chief Operating Reactors Branch #1 U.S. Nuclear Regulatory Commission Washington, D.C.

20555

Dear Mr. Schwencer:

NRC IE BULLETIN NO. 79-07 SUPPLEMENTAL RESPONSE NO. 1 SALEM GENERATING STATION DOCKET NO. 50-272 In our letter to you of October 11, 1979, we described our program for the reanalysis and modification of supports, nozzles and penetrations after entering Mode 2.

We called this Phase III of our program.

The purpose of this letter is to amend the Phase III program to read as follows:

1.

We shall complete reanalysis of the remaining pipe supports outside containment and shall propose a schedule for implementation of all identified modifications, both within sixty (60) days of the date of plant startup.

2.

For each modification identified as a result of reana3ysis of the supports outside containment after resumption of facility operation, when the overall margin of safety of the support to ulti-mate capacity is determined to be less than 2, the NRC shall be notified within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after making each such determination.

The affected system shall be considered inoperable as that term is used in the facility Technical Specifications until the necessary modifications are implemented within the time frame allowed by the Technical Specifications unless a reanalysis of the affected piping system is performed with the overstressed support removed from the system to demonstrate system operable.

O W) e 3,04

=

7910260, Mq

Albert Schwencor, Chief 10-18-79 If you should require any additional information concerning this amendment to our commitment please feel free to contact t.s.

Very truly yours, 1/b/-L/%,

Frank P.

Lib 2;id z,i General Manager -

Electric Production 1216 7,06